ID 223092987 © Ahmet Yamak | Dreamstime.com
Based on the 2023 NEC.
Question: What signage is required when a building has more than one service due to capacity requirements?
See answer below.
Answer: A permanent plaque or directory shall be installed at each service disconnect location denoting all other services, feeders, and branch circuits supplying that building or structure and the area served by each.
Explanation: The answer to this question comes from Sec. 230.2(E).
Lupacchino is a senior design engineer with Gaylor Electric, Inc. in Noblesville, Ind. and serves as an alternate on NEC Code-Making Panel No. 3. He is currently licensed in more than 80 jurisdictions. He can be reached at [email protected]