Fig. 4. How using application of ASTM E2691-20 can show prediction of job profitability in advance.

Project Gain or Fade

April 13, 2022
Why lack of visibility to the realities on the job site impacts profitability

You have many jobs of varying sizes. If we ventured a guess, we’d say that rarely do these jobs deliver the profit that was identified in the estimate. And if they do, the portion of the job where you made the profit was likely not where you expected to get it. How do we know this? Based on 30 years of studying the construction industry and data on millions of hours of construction projects, almost no projects turn out how they were bid. The root cause is a lack of visibility to the realities on the job site.       

Take a look at Fig. 1. MCA, Inc.’s data shows that while the estimates planned for a profit range of 12% to 24%, at the end of the job, the range was actually -12% to 42%. It’s difficult to comprehend this because the team believes and intends to be observing, discussing, and attempting to monitor the job throughout its lifecycle. But the numbers don’t lie.

Ask yourself these questions:

  • How often have you and your team watched the accounting job cost report and watched the burn rate on the job?
  • How often do you see job profit projections “holding steady” month after month?
  • How much attention do you put into your schedule of values to ensure you’re working to avoid financing the job?
  • How often do you review under and overbilling?
  • How often do you have work in progress meetings to discuss the status of the job?

You spend all this time with your team, reviewing the numbers, but you still end up with an outcome you don’t expect. So what are you missing?

Identifying the variation

Companies have various methods of tracking costs and profits. There are signs that things aren’t as stable as you’d like. You meet weekly, reviewing the status of the job by looking at the costs and the billings. It all looks under control, but then something changes at the end. The discussions throughout the job could include some of the following items: 

  • Depending on your method of tracking, you may hear that the percent complete of the job matches the percent labor spend through most of the job — until the end.   
  • If the labor is over budget, you may hear that “we’re waiting on approved change orders.”
  • When you’re close to substantial completion, you’ll hear that “we’re almost done,” but then that last 5% takes a LONG time to get to 100%.
  • You’re in the project management/work in progress meetings, asking or answering questions about projected profitability on the job and you hear, “We’re on track. There are no changes to report. Everything is going fine.”

MCA’s data in Fig. 2 shows that the real costs on the project – if labor and job productivity are not tracked – will likely show up when the job is close to 95% complete. And then what?! You have that last (long) 5% to finish and there aren’t a lot of knobs to turn to recover if you’re behind, or even explain why you’re ahead.

How can you help the situation?

The old saying is as true today as when it was first said: “What gets measured gets done.” It is also true that only what is visible gets measured. This takes a reference point/yardstick to measure performance against. This takes real-time data between estimating, the field, and accounting to triangulate to ensure that the answers you’re getting in those meetings are grounded in data. Figure 3 is an example of a report that links money, manpower, and material from the field, accounting, and estimating. The best way to predict profitability is to control the job during the job. The key to this is to measure productivity instead of production. Refer to ASTM E2691-20, Standard Practice for Job Productivity Measurement, which was originally published in 2008 and republished in 2012. The questions you should ask are:

  • Do the hours/labor/cost codes planned for the job match how the field sees/will build the job?
  • Are the cost codes being managed weekly to check for under/overruns (versus one large bucket of labor)?
  • How much work was planned for today versus how much was completed? If the completion didn’t meet the plan, why not, and what are you doing to help that?
  • What got in the team’s way of completing their work?

Putting it all together

Figure 4 shows a real-life example of a team using all of the points listed above (accounting cost reviews and project management percent complete projections) and following the recommendations in the ASTM E2691-20 Standard. Using the standard and labor productivity (versus production), the signals that the labor was not productive and the profitability of this job was at risk were present as early as March 2019 (when the job started up and the estimate/planned work had a difference). Then in May, the tool showed downward productivity. Since this was a five-month job, this early notification was quite significant — and likely could’ve helped job profitability if acted upon. The ending accounting/company reports confirmed what the tool using ASTM Standard E2691-20 had been displaying.        

So,  let’s focus on how you can use this process. First, create your reference points:

  • Track costs in your accounting/project management/work-in-progress meetings, but recognize you need a link to an independent reference point related to the completion of work.
  • Don’t go by gut feel for percent complete on the job. Watch this plan frequently. Take job walks, review with your team what they see in the field, and help them see things they may be missing.
  • Get the field workers to document the work they see on the job. Write it down with a daily plan. Don’t focus on what was completed by the end of the day, but on what you scheduled. Then note what got in your way, according to the article “The Secret to Short-Interval Scheduling.”
  • If they’re spending time mobilizing/demobilizing for other trades or general contractor requests, document it and the time you’re losing.
  • If they’re spending time moving material, consider breaking down the work to tasks you can have different people (or vendors) help with to keep your most valuable and skilled labor doing what they do best – installing. For more information on this concept, read the article “Real Ways to Reduce Material Handling Costs.”
  • Figure out anything that can be taken off the job site and completed in a pre-fab shop to help with safety and speed of installation, according to the article “Putting Prefab into Perspective.” 

If you focus on data and linking estimating, accounting, and field information through an application applying ASTM E2691-20’s Standard Practice for Job Productivity Measurement, you will not be surprised in the last 95% of the job. You’ll be able to effectively predict your profits to accurately plan for the future.

Dr. Heather Moore is the Co-Chair of ASTM Building Economics Subcommittee E06-81 and the vice president of operations at MCA, Inc., Grand Blanc, Mich. She can be reached at [email protected]Jennifer Daneshgari is vice president of financial services and operations at MCA, Inc. She can be reached at [email protected].

Voice your opinion!

To join the conversation, and become an exclusive member of EC&M, create an account today!

Sponsored Recommendations

Latest from Business Management

ID 335485132 © Imaginiac . | Dreamstime.com
The Top 5 Electrical and Construction Industry Trends for 2025
In the typical facility, the plant manager has X amount of discretionary spending power that can be directed toward a single purchase. At each level of management down, discretionary spending is stepped down into smaller amounts. Anything beyond a given manager’s limit must be appealed to the next level up. For example, the Plant Engineer can’t quite swing a purchase of $5200 but the Plant Manager can approve it. This informal arrangement reduces corporate overhead and improves operational efficiency. It does not address whether the spending decisions would make financial sense to the Chief Financial Officer, but the cap at each level keeps any mistakes to a reasonably acceptable loss or misallocation of resources. Beyond the Plant Manager’s limit, there is usually a formal process for getting spending approval. It typically involves filling out a Capital Request (or similarly named form). In well-run companies, the form is very structured. It mostly wants some basic information that will give the reviewer(s) the ability to justify not just the purchase but also the cost of acquiring the capital to do so. Because the funds will typically be borrowed by the corporation, the cost of capital must be balanced against the return on investment. There will be at least one person crunching the numbers to make what is called “the business case” for the proposed spending. Making the business case is something you should do, in some way or another, when considering spending within your approved limits. If the spending is above your approved limits, then the manager above you will need a bit beefier of a business case. The business case must take into account the value obtained versus the money spent. Consider the purchase of a thermographic camera. If you intend to purchase a mid-range camera but nobody at your facility is trained and certified in its use, the purchase is probably a waste of money. You’d be better off getting an entry-level camera and then arranging for a path toward certification if you intend to have that ability in-house and it makes operational and financial sense to do so. And generally, it makes sense to have a person or two with Level I certification so they really understand how to get the most out of a camera system that’s beyond the basic level. On the other hand, if you were a manager at an electrical testing firm with several Level III Thermographers you would be wasting your thermographers if you decided to “save money” by equipping them with only basic or even intermediate camera systems. Your firm needs to be able to troubleshoot problems when that important client calls in a panic. Your thermographers need the tools to do that job, and “cost-saving” on camera systems won’t cut it. Presumably, your clients are smart enough to already have basic camera systems; they just don’t have the expertise to use advanced systems. Sometimes a different logic applies to other types of test equipment. In the typical plant, maintenance electricians need sophisticated DMMs. If they lack the training to use the features that are needed for most effectively keeping equipment running, simply choosing a less capable DMM they already know how to use is not the answer. They need the appropriate DMM along with the training on how to use those features correctly. So far, we haven’t looked at the need to crunch any numbers to make the business case. What we have done is think about the match between the purchase, the problem that needs to be solved, and the ability of the user to solve the problem using that purchase. This sounds like a common sense approach that everyone would naturally take, but people often lose sight of the reason for the purchase in the first place. The tendency is to either go all out on something they can’t use or don’t need, or to “save money” by shortchanging the end users with something that doesn’t allow them to do what they need to do. What about those numbers? When you do a purchase request, a bean counter is going to try to determine the cash flows involved (typically in monthly periods). If you write something like, “The payback period is three years,” they don’t find that helpful. Lenders care that a loan can be serviced, and cash flow is the critical factor in calculating whether it can. Thus, beancounters don’t use payback to determine whether they can afford to borrow. They use the Internal Rate of Return (IRR) or Modified Internal Rate of Return (MIRR). Formulas for both IRR and MIRR have been in spreadsheet programs for over two decades, but before that they were determined using a Business Math Calculator (about $150 in 1990). And before that, they were laboriously calculated by hand. The cash flows that are charted will be either additional revenue generated or losses prevented. To help the person who figuratively wears the green eye shade, tie the use of the test equipment to a revenue stream. A major appliance plant in Tennessee has several production lines that collectively produce $1,560,000 per hour of revenue. Thus each minute of unplanned downtime is quite costly. If the plant electrical engineer there wanted to upgrade test equipment in a way that exceeds the Plant Manager’s spending authority, he needs to help the green eye shade guy do the math. He can cite short case histories from the past two years and briefly explain how having X capability (present in the new equipment, absent in the existing equipment) would have saved Y minutes of downtime (which the green eye shade guy will calculate out in terms of revenue and cash flow). The green eye shade guy also needs to know whether each case history is a one-off that will never recur or if it’s representative of what to expect in the future. You can settle this question with a brief explanation. For example, “The responding technician did not have a [name of test equipment]. Consequently, he had to arrive at the same conclusion by other means to the tune of 24 minutes of downtime he would not have incurred if he’d had a [name of test equipment]. This problem occurred once on Line 2 and twice on Line 4.” Now the green eye shade guy can simply add up the downtime, monetize it, and create the cash flow analysis. And it’s really good for something like a power monitor. For example, “In this particular case the plant did not have a monitoring system capable of detecting short-term bursts of power, which we call transient spikes, and alerting us. Transients happen with no notice, and usually without being detected. The motor shop forensic report shows the main motor failed due to winding insulation failure caused by transients. With a power monitor detecting and reporting those transients, we would have been able to intervene before outright failure, on a scheduled basis. That would have reduced downtime by 57 minutes twice last year alone.” Making the business case for your smaller purchases means simply thinking about what you are trying to accomplish and then making sure you are spending the funds correctly to achieve that goal. But as you go up the food chain, you need to make the picture more clear. And when you appeal to corporate for approval, you need to provide reasonably accurate downtime savings numbers that can be converted by them to revenue loss prevention in specific dollar amounts.
Man staring at wall with hand-drawn question marks and money bags on it

Sponsored