Illustrated Catastrophes

Sept. 1, 2007
As usual, never consider the following commentary associated with these photos as a formal interpretation of the National Electrical Code (NEC). Without criticizing anyone or any product, the following scenarios present us with serious safety questions. All references are based on the 2005 NEC. KEEP IT COOL Thomas H. Ford, a partner of Bhamani, Ford & Associates, Inc., Miami, found these unique panels

As usual, never consider the following commentary associated with these photos as a formal interpretation of the National Electrical Code (NEC). Without criticizing anyone or any product, the following scenarios present us with serious safety questions.

All references are based on the 2005 NEC.


KEEP IT COOL

Thomas H. Ford, a partner of Bhamani, Ford & Associates, Inc., Miami, found these unique panels in a restaurant. “On the top of each panel an inline fan has been installed to provide ventilation for the interior of the panel,” says Ford. “This was done because the vestibule, where the panels are located, is so warm that the breakers would trip. The fans solved this problem, but created another. The kitchen air is so laden with cooking oil particulate that when it is forced into the panel the cooking oil settles on the interior components. After the gutter was installed, the walls were tiled, covering the left side of the panel. Screws hold the cover to the gutter. This now means the cover can't be removed.”

When you think about “conditions of use,” you must take into account the ampacity of the conductors (Art. 100) and make sure they don't exceed their temperature rating [110.14(C)]. You must do the same for the conductor terminations. It's hard to imagine the original installer addressed this in the initial design. But one thing is for sure: The practice of installing makeshift ventilation systems to minimize overheating problems should not be allowed or tolerated by anyone.






MOVE THE RECEPTACLE OR THE WALL?

Mark Gravill, a service technician with Gaylor in Phoenix, found this unique situation on the roof of a building. “I'd say either move the receptacle or move the wall,” says Gravill.

It's apparent that the electrician was here first, so the wall must go! I'm not sure of the circumstances at this specific location, but it looks like the right type of cover was used, and it's probably GFCI protected in accordance with 210.8 and 406.8(A) and (B).


Found a Code violation? E-mail your text and photos (no cell phone images please) to Joe Tedesco at [email protected]

About the Author

Joe Tedesco

Tedesco served the industry in many roles during his career. He was a director, senior electrical code instructor for National Technology Transfer, Inc. and American Trainco, Inc.. He was also a codes, standards and seminar specialist for the International Association of Electrical Inspectors and an electrical field service specialist for the National Fire Protection Association in Quincy, Mass. He ran his own business as an NEC consultant and is a Massachusetts licensed master electrician and journeyman electrician and certified electrical inspector (one and two family 2A; General 2B, and Plan Review, 2C). Tedesco also wrote articles for CEE News and EC&M (Code Violations Illustrated and What's Wrong Here?) for more than 15 years and helped launched the Moving Violations video series.

Voice your opinion!

To join the conversation, and become an exclusive member of EC&M, create an account today!

Sponsored Recommendations

Electrical Conduit Comparison Chart

CHAMPION FIBERGLASS electrical conduit is a lightweight, durable option that provides lasting savings when compared to other materials. Compare electrical conduit types including...

Don't Let Burn-Through Threaten Another Data Center or Utility Project

Get the No Burn-Through Elbow eGuide to learn many reasons why Champion Fiberglass elbows will enhance your data center and utility projects today.

Considerations for Direct Burial Conduit

Installation type plays a key role in the type of conduit selected for electrical systems in industrial construction projects. Above ground, below ground, direct buried, encased...

How to Calculate Labor Costs

Most important to accurately estimating labor costs is knowing the approximate hours required for project completion. Learn how to calculate electrical labor cost.