Fill in the blank with the appropriate answer.

When installing a service mast, the hubs used with the conduit that serve the service mast shall be _____________.

  1. any type of hub.
  2. identified for use with service-entrance equipment.
  3. identified for use with feeder conductors.
  4. listed for grounding.

See answer and applicable Code reference

The correct answer is: 2) identified with use for service-entrance equipment

Section 230.28(A) of the 2014 NEC requires hubs to be identified for use with service-entrance equipment.

Owen is the owner and president of National Code Seminars and the holder of master electrician certifications in 46 states. He can be reached at [email protected].

About the Author

Steven Owen

Voice your opinion!

To join the conversation, and become an exclusive member of EC&M, create an account today!

Sponsored Recommendations

Electrical Conduit Comparison Chart

CHAMPION FIBERGLASS electrical conduit is a lightweight, durable option that provides lasting savings when compared to other materials. Compare electrical conduit types including...

Don't Let Burn-Through Threaten Another Data Center or Utility Project

Get the No Burn-Through Elbow eGuide to learn many reasons why Champion Fiberglass elbows will enhance your data center and utility projects today.

Considerations for Direct Burial Conduit

Installation type plays a key role in the type of conduit selected for electrical systems in industrial construction projects. Above ground, below ground, direct buried, encased...

How to Calculate Labor Costs

Most important to accurately estimating labor costs is knowing the approximate hours required for project completion. Learn how to calculate electrical labor cost.