Code Quiz

Oct. 8, 2009
What is the required minimum depth of the working space in the direction of live parts?

A question has arisen related to whether a storage battery installation has the required working space in accordance with the 2008 National Electrical Code. The depth of the battery rack supporting the batteries is 12 inches. It's installed tight against a concrete wall. Directly across from the battery rack is electrical switchgear rated at 600V, with a nominal operating voltage of 480V.

Based on these facts, what is the required minimum depth of the working space in the direction of live parts?

  1. 36 in. from the back edge of the battery rack to the front edge of the electrical switchgear.
  2. 42 in. from the front edge of the battery rack to the front edge of the electrical switchgear.
  3. 48 in. from the front edge of the battery rack to the terminals inside of the electrical switchgear.
  4. 48 in. from the front edge of the battery rack to the front edge of the electrical switchgear.

Answer: D

Article 480 focuses on storage batteries. As noted in 480.9(C), "Working space about the battery systems shall comply with 110.26. Working clearance shall be measured from the edge of the battery rack."

We can determine the required clearances from Table 110.26(A)(1). This particular installation falls under Condition 3, which covers "exposed live parts on both sides of the working space." Looking at the second row (151V to 600V) under the third column (Condition 3) we see that the installation calls for a minimum clearance of 4 ft.

Owen is the owner and president of National Code Seminars and the holder of master electrician certifications in 46 states. He can be reached at [email protected].

About the Author

Steven Owen

Voice your opinion!

To join the conversation, and become an exclusive member of EC&M, create an account today!

Sponsored Recommendations

Electrical Conduit Comparison Chart

CHAMPION FIBERGLASS electrical conduit is a lightweight, durable option that provides lasting savings when compared to other materials. Compare electrical conduit types including...

Fiberglass Electrical Conduit Chemical Resistance Chart

This information is provided solely as a guide since it is impossible to anticipate all individual site conditions. For specific applications which are not covered in this guide...

Considerations for Direct Burial Conduit

Installation type plays a key role in the type of conduit selected for electrical systems in industrial construction projects. Above ground, below ground, direct buried, encased...

How to Calculate Labor Costs

Most important to accurately estimating labor costs is knowing the approximate hours required for project completion. Learn how to calculate electrical labor cost.