Disregarding exceptions, which enclosure is limited to 30-foot (maximum) extensions beyond the equipment it supplements?

Q. Disregarding exceptions, which enclosure is limited to 30-foot (maximum) extensions beyond the equipment it supplements?

  1. Metallic wireways, only where limited to a maximum of 30 current-carrying conductors.
  2. Nonmetallic wireways, only where limited to a maximum 20% fill for all conductors.
  3. Busways, as long as the busway is not supplying and supporting flexible cords and cables.
  4. Auxiliary gutters.

Answer: D

As per 366.12 (Uses Not Permitted), “Auxiliary gutters shall not be used under the following conditions:
“(1) To enclose switches, overcurrent devices, appliances, or other similar equipment.
“(2) To extend a greater distance than 9 m (30 ft) beyond the equipment that it supplements.”

Note: The exception and FPN from this section of the Code are not listed here.

Owen is the owner and president of National Code Seminars and the holder of master electrician certifications in 46 states. He can be reached at [email protected].

About the Author

Steven Owen

Voice your opinion!

To join the conversation, and become an exclusive member of EC&M, create an account today!

Sponsored Recommendations

Electrical Conduit Comparison Chart

CHAMPION FIBERGLASS electrical conduit is a lightweight, durable option that provides lasting savings when compared to other materials. Compare electrical conduit types including...

Fiberglass Electrical Conduit Chemical Resistance Chart

This information is provided solely as a guide since it is impossible to anticipate all individual site conditions. For specific applications which are not covered in this guide...

Considerations for Direct Burial Conduit

Installation type plays a key role in the type of conduit selected for electrical systems in industrial construction projects. Above ground, below ground, direct buried, encased...

How to Calculate Labor Costs

Most important to accurately estimating labor costs is knowing the approximate hours required for project completion. Learn how to calculate electrical labor cost.