What's Wrong Here?

Oct 12, 2007 11:00 AM, By Joe Tedesco, NEC Columnist

Hint: Think Too-Tall Jones

”This 240V, 3-phase, 3-wire panelboard features 2- and 3-pole breakers,” says Ray Larsen, a professional engineer with PacifiCurrent Electrical Engineering in La Crescenta, Calif. “Since the breakers are not used as switches, is this a legal installation (besides having a missing cover)? The remaining breakers in use serve the building's HVAC units. The other enclosure to the right is also a 240V, 3-phase, 3-wire panel. One breaker feeds a 240V receptacle.”

This installation violates several NEC rules.

As per 240.24(A), “Overcurrent devices shall be readily accessible and shall be installed so that the center of the grip of the operating handle of the switch or circuit breaker, when in its highest position, is not more than 2.0 m (6 ft 7 in.) above the floor or working platform unless one of the following applies:
“(1) For busways, as provided in 368.12.
“(2) For supplementary overcurrent protection, as described in 240.10.
“(3) For overcurrent devices, as described in 225.40 and 230.92.
“(4) For overcurrent devices adjacent to utilization equipment that they supply, access shall be permitted to be by portable means.”

In addition, 404.8 states, “All switches and circuit breakers used as switches shall be located so that they may be operated from a readily accessible place. They shall be installed such that the center of the grip of the operating handle of the switch or circuit breaker, when in its highest position, is not more than 2.0 m (6 ft 7 in.) above the floor or working platform.” There are three exceptions to this rule, but none apply in this particular installation.

> Try Another Quiz

Want to use this article? Click here for options!

Code Challenge

Code Quiz

Nov 5, 2009 5:24 PM, By Steven Owen

What are the minimum and maximum lengths permitted for the grounding conductor on network-powered broadband communications systems network interface units that contain protectors?...


More Code Quizzes

Code Q&A

Nov 5, 2009 5:30 PM, By Mike Holt

When are tamper-resistant receptacles required?...


More Code Q&As
 


Acceptable Use Policy
blog comments powered by Disqus

what's wrong here?

What's Wrong Here?

Nov 5, 2009 11:50 AM

What's Wrong Here?

Oct 22, 2009 11:16 PM

What's Wrong Here?

Oct 8, 2009 3:32 PM

View all What's Wrong Here?

product of the week

Video camera scopes

November 16, 2009

Video camera scopes

View all 2009 Products of the Week

Recent Comments

More...


EC&M TV

Exterior Fixture Box for Brick or Stone

Installing a fixture box in a brick or stone wall just got easier with Arlington’s new adjustable depth box!

Southwire's 2009 Cable Innovation Road Show

Gain years worth of insight in only 2-1/2 hours with Southwire’s 2009 Cable Innovation Road Show with Grounding Seminar. The agenda is packed with valuable information that focuses on installation tips!

Listen
Sizing Gen-Sets: Facts, Hints, and Good Judgment
Listen

The complexities of today’s commercial or industrial facility, with their equipment environment of linear and nonlinear loads, places a whole new light on sizing engine-generator sets.

Arc Mitigation - A Total System Approach
There’s no question the risk of arc flash hazards is real in the electrical industry. What many don’t always realize is the impact in business interruption from such events typically far outweighs the physical damage to equipment. View this On Demand Webinar!

Implementing an Industrial Ethernet Infrastructure that's Built to Last
This webinar explores the key benefits of implementing a robust complete, end-to-end Industrial Ethernet solution – from cabling and connectivity, to active components and associated hardware. View this On Demand Webinar!

resources

product info icon

product info

tradeshow icon

tradeshow

research icon

research

rss icon

rss

Browse Back Issues

Browse Back Issues