What's Wrong Here?

May 6, 2010 12:08 PM, By Brian J. McPartland, NEC Consultant

Hint: ’Tis the wrong season

Here we see an all-too-common violation of the requirements set forth in 590.3(B). This section of the Code says, "Temporary electric power and lighting installations shall be permitted for a period not to exceed 90 days for holiday decorative lighting and similar purposes." Given the fact that this picture is of a house in the northeastern United States — and the trees are in full bloom — it’s safe to assume that the 90-day limit imposed by this Code rule has been exceeded. As such, the "icicle" lighting string should have been removed at some point prior to the time when this picture was taken.

Although this is a very common violation, it's rare that a property owner — whether the occupancy is classified residential or commercial — is cited for failure to remove Christmas lighting within the prescribed time frame. This reality is a function of enforcement. Third-party inspection agencies have no authority to go on private property, unless invited, and inspectors for municipal building departments are either not aware of the rule or not concerned.

It's worth noting that the "hard-and-fast" 90-day limit placed on seasonal lighting is the only instance where the Code places any time constraint on "temporary installations" for light and power. The other referenced applications in Sec. 590.3 focus on are permitted to be used as long as needed. However, as noted in part (D) of this rule, "Temporary wiring shall be removed immediately upon completion of construction or purpose for which the wiring was installed." This wording essentially requires temporary wiring to be removed as soon as possible.

This is a "make-sense" proposition, because, as we know, the installation requirements in Art. 590 are less stringent than those given for permanent wiring. While such relaxing of the general requirements is needed during those instances identified in Sec. 590.3, it’s not the safest — especially where the general public has access to the location — and it should only be used as long as absolutely needed.

> Try Another Quiz

Want to use this article? Click here for options!

Code Challenge

Code Quiz

May 10, 2012 12:29 PM, By Steven Owen, National Code Seminars

When installing a shielded cable or a twisted pair cable in a Class I, Division 1 location where a cable seal is required, when is it not required to remove the shielding material or separate the twisted pairs of those type cables?...


More Code Quizzes

Code Q&A

May 24, 2012 10:42 AM, By Mike Holt, NEC Consultant

Q. What labeling does the Code require in regard to arc flash hazard warning?...


More Code Q&As
 



Acceptable Use Policy
blog comments powered by Disqus

what's wrong here?

What's Wrong Here?

May 10, 2012 12:44 PM

What's Wrong Here?

Apr 19, 2012 10:09 AM

What's Wrong Here?

Apr 5, 2012 2:27 PM

View all What's Wrong Here?

product spotlight

EV charger tester

May 25, 2012 8:26 AM

EV charger tester

The Electrician is portable tester that verifies critical power and safety requirements of electric vehicle (EV) chargers...

View all 2012 Product Spotlights

Free Product Info

Our Product Information site is the ultimate online resource for products and services offered by Advertisers featured in our Magazine. This service is provided as a quick and easy way to request Product Information online. Get FREE product information now.

Recent Comments

More...


Social Media

More ways to stay informed...

follow us on twitter

Find us on Facebook

EC&M Whitepaper

Arc Mitigation –A Three-Step Approach

Did you know that an arc-flash incident hospitalizes 5-7 workers per day in North America, severely impacting processes and profitability with lost production? Download This Sponsored Whitepaper Today!

What's New in Residential Cabling?
Date: Wednesday, May 30, 2012
Time: 2:00pm ET


In this The Home Depot sponsored Low Voltage Webinar, Ron Kipper RCDD / NTS will discuss the need for compression style coaxial connectors and the migration of the entire CATV, Satellite and Audio / Video industry to them. Register Today!

Grounding Versus Bonding
Now Available On-Demand


In this 60-minute FREE webinar, Mike Holt of Mike Holt Enterprises, Inc. will explain the purpose of grounding and bonding as related to the most current requirements set forth in the 2011 NEC. Register to View On-Demand!

resources

product info icon

product info

tradeshow icon

tradeshow

research icon

research

industry links

industry links

rss icon

rss

Browse Back Issues

Browse Back Issues