What's Wrong Here?
Mar 23, 2005 9:41 AM, By Joe Tedesco
Answer:
Hint: Maybe the electrician was in a hurry to get temporary power to this building.
Reader Doug Kidd of Kincaid*Bryant, in Lynchburg, Va., found this installation recently while designing a chiller replacement at a state college. The original installation was part of a major building renovation in 1985. The design included a 2,000A high-pressure contact main switch in the switchboard as the building service disconnect.
Aside from this, the electrician had only installed three parallel sets of 500 kcmil as the service lateral, per the design specifications.
Kidd advised the Owner to immediately replace the so-called fuses and included adding a new service lateral to the design.
Want to use this article? Click here for options!
© 2010 Penton Media, Inc.
Code Challenge
Code Quiz
Mar 11, 2010 12:45 PM, By Steven Owen
When installing outlet boxes for wall-mounted luminaires, when can you use No. 6 screws to secure the luminaire yoke to a plaster ring?...
More Code Quizzes
Acceptable Use Policy blog comments powered by Disqus
advertisement
what's wrong here?
|
Whats Wrong Here?Mar 11, 2010 12:54 PM |
|
What's Wrong Here?Feb 18, 2010 5:04 PM |
|
What's Wrong Here?Feb 4, 2010 5:06 PM |
View all What's Wrong Here?
What's Wrong Here
Sponsored By:

Email