What's Wrong Here?

Jan 1, 2007 12:00 PM, By Joe Tedesco, NEC Columnist

Answer:

Hint: Look out for those orange barrels in the sky.

Mitchell Brochu, a student at a local trade school in Philadelphia — who's been working in the field for about eight months — noted the following Code violations with the January photo: Sections 230.9(A), 230.27, 230.50(A), 230.54(A), and 230.54(F). “I hope I got it right,” says Brochu. “I could use those insulated hand tools!”

Brian N. Ferreira, an assistant estimator with Consolidated Electrical Services in Norwood, Mass., had this to say. “As for the obvious violation with the orange boot used to protect the service drop connections, I looked to Art. 230 (Services) and found the following:

“230.9 Clearances on Buildings. Service conductors and final spans shall comply with 230.9(A), (B), and (C).

“(A) Clearances. Service conductors installed as open conductors or multiconductor cable without an overall outer jacket shall have a clearance of not less than 3 ft from windows that are designed to be opened, doors, porches, balconies, ladders, stairs, fire escapes, or similar locations.

“(B) Vertical Clearance. The vertical clearance of final spans above or within 3 ft measured horizontally of, platforms, projections, or surfaces from which they might be reached shall be maintained in accordance with 230.24(B).

“I also like how they extended the service drop conductors to accommodate the lack of slack to make the connections to the service conductors. At least they didn't need a ladder to make the final connections!”

Charles Smith, an electrical development engineer in Circleville, Ohio, also cited a violation of Sec. 230.9 in this installation.

> Try Another Quiz

Want to use this article? Click here for options!

Code Challenge

Code Quiz

Feb 2, 2012 9:02 PM, By Steven Owen

When installing audio distribution cables exposed on the surface of ceilings and sidewalls, the cables shall be supported by which of the following products?

    ...


More Code Quizzes

Code Q&A

Feb 2, 2012 8:58 PM, By Mike Holt

Q. Is it acceptable to use a 14 AWG conductor for the bonding jumper to a receptacle on a 20A branch circuit?

...


More Code Q&As
 



Acceptable Use Policy
blog comments powered by Disqus

what's wrong here?

What's Wrong Here?

Feb 2, 2012 7:54 PM

What's Wrong Here?

Jan 19, 2012 4:06 PM

What's Wrong Here?

Jan 5, 2012 11:53 AM

View all What's Wrong Here?

product spotlight

Labeling tool

Feb 10, 2012 7:58 AM

Labeling tool

The Rhino 4200 labeling tool features one-touch “hot keys” that quickly create and format wire/cable wraps, flags, fixed-length labels and more...

View all 2012 Product Spotlights

Free Product Info

Our Product Information site is the ultimate online resource for products and services offered by Advertisers featured in our Magazine. This service is provided as a quick and easy way to request Product Information online. Get FREE product information now.

Recent Comments

More...


Social Media

More ways to stay informed...

follow us on twitter

Find us on Facebook

EC&M TV

Arlington CP9000

Arlington's new 9" diameter ceiling cover plate is the neatest way to cover unused "high hat" cans. With no tools needed, installation couldn't be faster!...

Arlington Gangable Boxes

Designed for new or retrofit applications, these snap-together gangable plastic boxes eliminate the need to construct a multiple-gang steel box out of several individual ones...

Understanding NEC Requirements for Solar Photovoltaic Systems
During this session, Mike Holt will address possible conflicts or confusing NEC requirements, provide tips on proper electrical installation techniques, and discuss the dangers related to improper installations. View this On Demand Webinar!



resources

product info icon

product info

tradeshow icon

tradeshow

research icon

research

industry links

industry links

rss icon

rss

Browse Back Issues

Browse Back Issues