Illustrated Catastrophes

Jul 1, 2004 12:00 PM, By Joe Tedesco, NEC Columnist

More Code catastrophes

As usual, never consider the following commentary associated with these photos as a formal interpretation of the National Electrical Code (NEC). Without criticizing anyone or any product, the following scenarios present us with serious safety questions.






THE RIGGED RECEPTACLE

Randy Barnett, senior instructor, American Trainco, Engelwood, Colo., sent us this photo of what was left of a receptacle that was installed in a large Midwest hospital. The maintenance technician, who brought the receptacle to one of Barnett's training classes, said after he plugged in his vacuum cleaner and turned it on, the receptacle immediately exploded. Investigation by the hospital's electric shop revealed that the receptacle had been improperly connected to a 480V circuit. Luckily for him the vacuum wasn't on when he plugged into the receptacle.

You might ask yourself, How could a 120V receptacle be wired into a 480V system? During a recent remodeling project at the hospital, a contract electrician needed some temporary 480V power, so he rigged a 120V receptacle to get the job done. One can only wonder how he modified the plug he was using at the time. When asked about the situation, he said he simply forgot to disconnect it after he was done with his project. Aside from the fact that the installation violates the Code's requirements that prohibit the use of equipment for a purpose for which it's neither suitable nor listed (110.3), the issue raises questions about whether any such electrician could be considered qualified.


DOCKSIDE DISASTER

Bob Froehlich, vice president, Advance Electric, Robbinsville, N.J., received a call from a local township to visit a public marina that was requesting additional dockside outdoor marine-style pedestals that contain power receptacles for docked watercraft slips. The following note describes the conditions he found during his inspections:

“In my 26 years of experience I've viewed many commercial and industrial electrical installations and as-found conditions, but this installation of electrical work had me totally flabbergasted. The number of violations I took visual note of was beyond my imagination. This installation was so bad, I never asked the owner to unlock the outdoor post-mounted load center because I didn't want to see inside.”

The wiring methods shown in this photo violate many rules found in Article 334 and Article 555 of the Code. The exposed Romex that runs along the edge of the dock is only the tip of the iceberg.


WHERE'S THE METER?

A. K. Rosenhan, P.E., chief engineer for the State of Mississippi in Mississippi State, Miss., received this photo from a rural fire department in the state with the following note:

“Occasionally we see stuff like this, cheating the power company. In this case the house looked to be abandoned and uninhabitable, but when we got the fire put out and looked around a bit this is what we saw. The initial size up was no electrical hookup, not only the jumped meter, but the line back to the transformer was buried in debris from a partial collapse (prior to the fire) of the rear of the house.”

Not only is the theft of electricity illegal, but this installation could also be cited for not meeting the requirements of 110.2, 110.3, or 110.4 of the NEC.

Found a Code violation? Send your photos to Joe Tedesco at P.O. Box 130408, Boston, MA 02113 or electricalinspector@netzero.com.

Want to use this article? Click here for options!



Acceptable Use Policy
blog comments powered by Disqus

what's wrong here?

What's Wrong Here?

Nov 5, 2009 11:50 AM

What's Wrong Here?

Oct 22, 2009 11:16 PM

What's Wrong Here?

Oct 8, 2009 3:32 PM

View all What's Wrong Here?

product of the week

Video camera scopes

November 16, 2009

Video camera scopes

View all 2009 Products of the Week

Recent Comments

More...


EC&M TV

Exterior Fixture Box for Brick or Stone

Installing a fixture box in a brick or stone wall just got easier with Arlington’s new adjustable depth box!

Southwire's 2009 Cable Innovation Road Show

Gain years worth of insight in only 2-1/2 hours with Southwire’s 2009 Cable Innovation Road Show with Grounding Seminar. The agenda is packed with valuable information that focuses on installation tips!

Listen
Sizing Gen-Sets: Facts, Hints, and Good Judgment
Listen

The complexities of today’s commercial or industrial facility, with their equipment environment of linear and nonlinear loads, places a whole new light on sizing engine-generator sets.

Arc Mitigation - A Total System Approach
There’s no question the risk of arc flash hazards is real in the electrical industry. What many don’t always realize is the impact in business interruption from such events typically far outweighs the physical damage to equipment. View this On Demand Webinar!

Implementing an Industrial Ethernet Infrastructure that's Built to Last
This webinar explores the key benefits of implementing a robust complete, end-to-end Industrial Ethernet solution – from cabling and connectivity, to active components and associated hardware. View this On Demand Webinar!

resources

product info icon

product info

tradeshow icon

tradeshow

research icon

research

rss icon

rss

Browse Back Issues

Browse Back Issues