Jul 1, 2000 12:00 PM, By James Stallcup, Sr. and James Stallcup, Jr.

Although it's rather simple component, an equipment-grounding conductor (EGC) serves a vital role in your overall electrical system.

You use an equipment-grounding conductor (EGC) to ground the noncurrent-carrying metal parts of equipment. Its function is to keep your equipment as close as possible to ground potential and provide a safe path for ground-fault current to flow. A properly sized EGC protects circuit elements and equipment and ensures the safety of your personnel from electric shock. Let's take a closer look at installation guidelines.

The NEC allows you to install an EGC in a raceway, cable tray, cable armor, or cable sheath. Per Sec. 250-134(b) and Sec. 300-3(b), the EGC must be contained within the same raceway, cable, or otherwise run with circuit conductors. You size an EGC based on the size of the overcurrent protection device (OCPD) protecting the circuit conductors of the electrical circuit in question.

The sizing and installation of the EGC must conform to the rules of Sec. 250-122 and Table 250-122. Where you have to increase current-carrying conductors in size to compensate for voltage drop, adjust the EGC proportionately to the circular mil area per Sec. 250-122(b) . The NEC also permits you to run a single EGC with multiple circuits in the same raceway per Sec. 250-122(c), as long as you size it based on the largest overcurrent device protecting the conductors in the raceway or cable.

For example, if you route three No. 10, two No. 12 and three No. 14 conductors in the same raceway, you can pull a No. 10 EGC through the raceway to serve as a grounding means for all circuit conductors.

When you install a No. 6 or smaller EGC, the insulation along its entire length must be colored green or green with one or more yellow stripes. You can also use a completely bare EGC under certain conditions. If the job calls for an EGC that's larger than No. 6 copper or aluminum, it must be color-coded at each end and at every point where the conductor is accessible.

The NEC permits you to use the following methods to identify an EGC larger than No. 6:

• Stripping the insulation or covering from the entire exposed length.

• Coloring the exposed insulation or covering green.

• Marking the exposed insulation or covering with green colored tape or green adhesive labels.

When you're working with a motor circuit, where the OCPD consists of an instantaneous trip circuit breaker or a motor short-circuit protector (as allowed per Sec. 430-52), you must size the EGC based on the rating of the motor overload protective device. In any design, the EGC never has to be larger than the largest ungrounded phase conductor supplying the motor is.

Sometimes you're faced with running circuit conductors in parallel and routing them in separate conduits. In this case, you must run a separate EGC in each conduit. You size the EGC per Table 250-122, based on the rating of the OCPD protecting the circuit [as per Sec. 250-122(f)]. Note that you must install a full size EGC in each conduit. As you can see, the 1999 Code does a nice job of presenting the guidelines for the use of EGCs in a user-friendly format.

Don't miss EC&M Seminar's new Hazardous Location Wiring Conference, presented by James Stallcup, EC&M Contributing Editor and former Chief Electrical Inspector.

Want to use this article? Click here for options!



Acceptable Use Policy
blog comments powered by Disqus

what's wrong here?

What's Wrong Here?

Nov 5, 2009 11:50 AM

What's Wrong Here?

Oct 22, 2009 11:16 PM

What's Wrong Here?

Oct 8, 2009 3:32 PM

View all What's Wrong Here?

product of the week

Video camera scopes

November 16, 2009

Video camera scopes

View all 2009 Products of the Week

Recent Comments

More...


EC&M TV

Exterior Fixture Box for Brick or Stone

Installing a fixture box in a brick or stone wall just got easier with Arlington’s new adjustable depth box!

Southwire's 2009 Cable Innovation Road Show

Gain years worth of insight in only 2-1/2 hours with Southwire’s 2009 Cable Innovation Road Show with Grounding Seminar. The agenda is packed with valuable information that focuses on installation tips!

Listen
Sizing Gen-Sets: Facts, Hints, and Good Judgment
Listen

The complexities of today’s commercial or industrial facility, with their equipment environment of linear and nonlinear loads, places a whole new light on sizing engine-generator sets.

Arc Mitigation - A Total System Approach
There’s no question the risk of arc flash hazards is real in the electrical industry. What many don’t always realize is the impact in business interruption from such events typically far outweighs the physical damage to equipment. View this On Demand Webinar!

Implementing an Industrial Ethernet Infrastructure that's Built to Last
This webinar explores the key benefits of implementing a robust complete, end-to-end Industrial Ethernet solution – from cabling and connectivity, to active components and associated hardware. View this On Demand Webinar!

resources

product info icon

product info

tradeshow icon

tradeshow

research icon

research

rss icon

rss

Browse Back Issues

Browse Back Issues