Code Quiz

May 21, 2004 12:00 PM, By Steven Owen

Q. Two 480V motor control centers (MCCs) are located directly across the aisle from one another and face each other in an electrical distribution room. They’re exactly 48 inches apart, which complies with Table 110.26(A)(1) for a Condition 3 spacing requirement. One of the existing MCCs is set to be replaced with a new MCC that’s 5 inches deeper, but the existing MCC is set against a wall, so the new MCC will have to be installed in the exact location. This will cause the new MCC to extend 5 inches into the required working space between the two MCCs. The proposed installation will allow 43 inches between the MCCs (front-to-front). What is the minimum spacing required for this proposed installation to be Code compliant?

A) 48 inches
B) 43 inches
C) 42 inches
D) 36 inches

Answer: C

Explanation: In 110.26(A)(1)(c), the 2002 NEC permits a reduction of 6 inches by re-classifying a Condition 3 space to a Condition 2 space. This is reducing a 48-inch minimum space to a 42-inch minimum space. This is allowable when conditions of maintenance and supervision ensure that written procedures have been adopted to prohibit equipment on both sides of the aisle from being open at the same time, and qualified persons who are authorized will service the installation.

Owen is the owner and president of National Code Seminars and the holder of master electrician certifications in 46 states.

Want to use this article? Click here for options!



Acceptable Use Policy
blog comments powered by Disqus

what's wrong here?

What's Wrong Here?

Nov 5, 2009 11:50 AM

What's Wrong Here?

Oct 22, 2009 11:16 PM

What's Wrong Here?

Oct 8, 2009 3:32 PM

View all What's Wrong Here?

product of the week

LED light engine

November 2, 2009

LED light engine

View all 2009 Products of the Week

Recent Comments

More...


EC&M TV

Exterior Fixture Box for Brick or Stone

Installing a fixture box in a brick or stone wall just got easier with Arlington’s new adjustable depth box!

Southwire's 2009 Cable Innovation Road Show

Gain years worth of insight in only 2-1/2 hours with Southwire’s 2009 Cable Innovation Road Show with Grounding Seminar. The agenda is packed with valuable information that focuses on installation tips!

Listen
Sizing Gen-Sets: Facts, Hints, and Good Judgment
Listen

The complexities of today’s commercial or industrial facility, with their equipment environment of linear and nonlinear loads, places a whole new light on sizing engine-generator sets.

Arc Mitigation - A Total System Approach
There’s no question the risk of arc flash hazards is real in the electrical industry. What many don’t always realize is the impact in business interruption from such events typically far outweighs the physical damage to equipment. View this On Demand Webinar!

Implementing an Industrial Ethernet Infrastructure that's Built to Last
This webinar explores the key benefits of implementing a robust complete, end-to-end Industrial Ethernet solution – from cabling and connectivity, to active components and associated hardware. View this On Demand Webinar!

resources

product info icon

product info

tradeshow icon

tradeshow

research icon

research

rss icon

rss

Browse Back Issues

Browse Back Issues