Code Quiz

May 14, 2007 3:47 PM, By Steven Owen

Q. A contractor installed a 2,000A, 480V, 3-phase feeder in six separate raceways, consisting of a total of six 500kcmil XHHW insulated conductors per phase. Four of the raceways are 3-inch trade size EMT. The other two raceways are 3½-inch RMC. All conductors are exactly the same length, per paralleled phase, and feature the same insulation type and conductor material. In addition, all are terminated in the same manner and have the same cross-sectional area. The inspector has turned this installation down. What could possibility make this installation non-Code compliant?

    1. Nothing. This installation is Code compliant.
    2. The raceways are not the same. You must change all raceway sizes to either 3½-inch EMT or 3½-inch RMC.
    3. The raceways are not the same. You must change all raceways to either EMT or RMC of the proper trade size.
    4. The installation has an incorrect number of conductors paralleled. Change the number of conductors per phase from six to five.
Answer: C

Where run in separate raceways or cables, the raceways or cables shall have the same physical characteristics (i.e., same type conduit) [310.4]. In addition, the installation shall meet these five requirements:

    1. All conductors shall be exactly the same length per paralleled phase.
    2. All conductors shall have the same insulation type.
    3. All conductors shall be made of the same material.
    4. All conductors shall have the same cross-sectional area.
    5. All conductors shall be terminated in the same manner.

Owen is the owner and president of National Code Seminars and the holder of master electrician certifications in 46 states. He can be reached at necexpert@aol.com.

Want to use this article? Click here for options!



Acceptable Use Policy
blog comments powered by Disqus

what's wrong here?

What's Wrong Here?

Nov 5, 2009 11:50 AM

What's Wrong Here?

Oct 22, 2009 11:16 PM

What's Wrong Here?

Oct 8, 2009 3:32 PM

View all What's Wrong Here?

product of the week

LED light engine

November 2, 2009

LED light engine

View all 2009 Products of the Week

Recent Comments

More...


EC&M TV

Exterior Fixture Box for Brick or Stone

Installing a fixture box in a brick or stone wall just got easier with Arlington’s new adjustable depth box!

Southwire's 2009 Cable Innovation Road Show

Gain years worth of insight in only 2-1/2 hours with Southwire’s 2009 Cable Innovation Road Show with Grounding Seminar. The agenda is packed with valuable information that focuses on installation tips!

Listen
Sizing Gen-Sets: Facts, Hints, and Good Judgment
Listen

The complexities of today’s commercial or industrial facility, with their equipment environment of linear and nonlinear loads, places a whole new light on sizing engine-generator sets.

Arc Mitigation - A Total System Approach
There’s no question the risk of arc flash hazards is real in the electrical industry. What many don’t always realize is the impact in business interruption from such events typically far outweighs the physical damage to equipment. View this On Demand Webinar!

Implementing an Industrial Ethernet Infrastructure that's Built to Last
This webinar explores the key benefits of implementing a robust complete, end-to-end Industrial Ethernet solution – from cabling and connectivity, to active components and associated hardware. View this On Demand Webinar!

resources

product info icon

product info

tradeshow icon

tradeshow

research icon

research

rss icon

rss

Browse Back Issues

Browse Back Issues