Grounding - Art. 250

Choose the best answer:

1. What size copper grounded (neutral) conductor does the National Electrical Code (NEC) require if the service-entrance conductors are rated at No. 250kcmil THWN copper?

(a) No. 6

(b) No. 4

(c) No. 2

(d) No. 1/0

2. What size copper main bonding jumper does the NEC require if the service-entrance conductors are rated at No. 250kcmil THWN copper?

(a) No. 4

(b) No. 2

(c) No. 1/0

(d) No. 2/0

3. What size copper equipment-bonding jumper does the NEC require if the service-entrance conductors are rated at No. 250kcmil THWN copper?

(a) No. 2

(b) No. 1/0

(c) No. 2/0

(d) No. 3/0

4. What size copper grounding electrode conductor does the NEC require to ground a service to a metal water pipe supplied by No. 250kcmil THWN copper conductors?

(a) No. 8

(b) No. 6

(c) No. 4

(d) No. 2

5. What size copper grounding electrode conductor does the NEC require to supplement the metal water pipe in Question 4 to a driven rod?

(a) No. 8

(b) No. 6

(c) No. 4

(d) No. 2

answers and discussion

1. (c). The grounded (neutral) conductor must be routed with the ungrounded (phase) conductors and shall not be smaller than the required grounding electrode conductor (GEC), per Table 250-66. However, it's not required to be larger than the largest ungrounded service-entrance (phase) conductor. Note: The grounded (neutral) conductor must also comply with Secs. 220-22 and 310-15(b)(4)(c).

Step 1: Find the appropriate grounded (neutral) conductor, per Table 250-66.

Solution: No. 250kcmil Cu requires No. 2 Cu.

Stallcup's Code Loop: Secs. 250-24(b)(1), and 250-142(a)(1), and Table 250-66.

2. (b). The size of the service main bonding jumper (MBJ) is based on the size of the service-entrance conductors. You size it, per Table 250-66.

Step 1: Find the MBJ, per Table 250-66.

Solution: No. 250kcmil Cu requires No. 2 Cu.

Stallcup's Code Loop: Sec. 250-28(d) and Table 250-66.

3. (a). The size of the equipment-bonding jumper (EBJ) on the supply side of the service is based on the size of the service-entrance conductors. You size it, per Table 250-66.

Step 1: Size EBJ on supply side, per Table 250-66.

Solution: No. 250kcmil Cu requires No. 2 Cu.

Stallcup's Code Loop: Sec. 250-102(c) and Table 250-66.

4. (d). The procedure for selecting the proper size GEC to ground the service to a metal water pipe is determined based on the size of the service-entrance conductors. Note: There is no OCPD ahead of these conductors.

Step 1: Size the GEC, per Table 250-66.

Solution: No. 250kcmil Cu requires No. 2 Cu.

Stallcup's Code Loop: Secs. 250-66, 250-104(a), 250-50, and 250-50(a), and Table 250-66.

5. (b). You may install the copper tubing or metal water pipe in a new installation in the earth or above grade. Either installation requires an additional electrode to supplement the copper or metal water pipe. This additional grounding electrode must conform with Sec. 250-50(b) through (d) or Sec. 250-52(a) through (c).

Step 1: Size the GEC, per Sec. 250-66(a).

Solution: No. 250kcmil Cu requires No. 6 Cu.

Stallcup's Code Loop: Secs. 250-50(a)(2) and 250-66(a).

Next month's "Quizzes on the Code" will contain questions on sizing the grounded (neutral) conductor, main bonding jumper, and equipment-bonding jumper for a paralleled installation.

Each quiz on the 1999 National Electrical Code is provided with Stallcup's Code Loops to show the direct correlation with other sections of the NEC. This allows the reader to review other sections of the NEC when determining if the correct answer to a problem is in one or multiple sections of the Code.

Find More Code Quizzes »


Want to use this article? Click here for options!





Acceptable Use Policy
blog comments powered by Disqus

what's wrong here?

What's Wrong Here?

Feb 2, 2012 7:54 PM

What's Wrong Here?

Jan 19, 2012 4:06 PM

What's Wrong Here?

Jan 5, 2012 11:53 AM

View all What's Wrong Here?

product spotlight

Labeling tool

Feb 10, 2012 7:58 AM

Labeling tool

The Rhino 4200 labeling tool features one-touch “hot keys” that quickly create and format wire/cable wraps, flags, fixed-length labels and more...

View all 2012 Product Spotlights

Free Product Info

Our Product Information site is the ultimate online resource for products and services offered by Advertisers featured in our Magazine. This service is provided as a quick and easy way to request Product Information online. Get FREE product information now.

Recent Comments

More...


Social Media

More ways to stay informed...

follow us on twitter

Find us on Facebook

EC&M TV

Arlington CP9000

Arlington's new 9" diameter ceiling cover plate is the neatest way to cover unused "high hat" cans. With no tools needed, installation couldn't be faster!...

Arlington Gangable Boxes

Designed for new or retrofit applications, these snap-together gangable plastic boxes eliminate the need to construct a multiple-gang steel box out of several individual ones...

Understanding NEC Requirements for Solar Photovoltaic Systems
During this session, Mike Holt will address possible conflicts or confusing NEC requirements, provide tips on proper electrical installation techniques, and discuss the dangers related to improper installations. View this On Demand Webinar!



resources

product info icon

product info

tradeshow icon

tradeshow

research icon

research

industry links

industry links

rss icon

rss

Browse Back Issues

Browse Back Issues