Dec 1, 2000 12:00 PM, By James Stallcup

Grounding - Art. 250

Choose the best answer: 1. What size copper bonding jumper (BJ) should you use to bond/ground the secondary of a separately derived system to building steel? The circuit has four No. 3/0 THWN copper conductors.

(a) No. 6 (b) No. 4 (c) No. 2 (d) No. 1/0

2. What size copper grounding electrode conductor (GEC) should you use to bond and ground the secondary of a separately derived system to building steel? The circuit consists of four No. 3/0 THWN copper conductors.

(a) No. 4 (b) No. 2 (c) No. 1/0 (d) No. 2/0

3. In a paralleled 3-phase, 4-wire service with four 600kcmil THWN copper conductors per phase, what size BJ should you use to bond and ground the separately derived system to building steel?

(a) No. 3/0 (b) No. 4/0 (c) 250kcmil (d) 300kcmil

4. In a paralleled 3-phase, 4-wire service with four 600kcmil THWN copper conductors per phase, what size grounding electrode conductor should you use to bond and ground the separately derived system to building steel?

(a) No. 3/0 (b) No. 4/0 (c) 250kcmil (d) 300kcmil

5. What size grounding electrode conductor should you use to bond and ground the secondary of a separately derived system to a driven rod? The circuit consists of four No. 3/0 THWN copper conductors.

(a) No. 8 (b) No. 6 (c) No. 4 (d) No. 2

Answers and Discussion

1. (b). You must size the BJ based on the type and size phase conductors supplying the panel, switch, or other equipment connected to the secondary side of the transformer, per Secs. 250-28(d) and 250-102(c). The BJ shall not be smaller than the sizes shown in Table 250-66 for grounding electrode conductors.

Solution: Find BJ, per Table 250-66.

No. 3/0 THWN Cu requires a No. 4 Cu jumper.

Stallcup's Code Loop: Secs. 250-28(d), 250-30(a)(1), and 250-102(c), and Table 250-66.

2. (a). You must size the GEC based on the type and size phase conductors supplying the panel, switch, or other equipment connected to the secondary side of the transformer.

Solution: Find GEC size, per Table 250-66.

No. 3/0 THWN Cu requires a No. 4 Cu conductor.

Stallcup's Code Loop: Sec. 250 30(a)(2) and Table 250-66.

3. (d). In this case, since the total circular mil area of the paralleled copper service conductors is greater than 1100kcmil, you must size the BJ to be at least 12.5% greater than the area of the largest ungrounded (phase) conductor.

Step 1: Calculate total circular mil area of service conductors.

600kcmil x 4 = 2400kcmil.

Step 2: Calculate minimum size BJ, per Sec. 250-28(d) and 250-30(a)(1).

2400kcmil x .125 = 300kcmil.

Step 3: Select proper size BJ, per Table 8, Ch. 9.

300kcmil requires a 300kcmil jumper.

Stallcup's Code Loop: Secs. 250-28(d), 250-30(a)(1), and 250-102(c), and Table 250-66.

4. (a). Size the GEC, per Table 250-66. If the total circular mil area of the service conductors is greater than 1100kcmil copper and 1750kcmil aluminum, the GEC should be smaller than the BJ.

Step 1: Calculate total circular mil area of service conductors.

600kcmil x 4 = 2400kcmil.

Step 2: Select proper size GEC, per Table 250-66.

2400kcmil requires a No. 3/0 Cu conductor.

Stallcup's Code Loop: Secs. 250-28(d) and 250-30(a)(2), and Table 250-66.

5. (b). When connecting the GEC to a driven rod or other made electrodes, you size it, per Sec. 250-66(a). It isn't required to be larger than No. 6 copper wire.

Stallcup's Code Loop: Secs. 250-30(a) (3)(c), 250-52, 250-56, and 250-66(a).

Find More Code Quizzes »

Want to use this article? Click here for options!




Acceptable Use Policy
blog comments powered by Disqus

what's wrong here?

Whats Wrong Here?

Mar 11, 2010 12:54 PM

What's Wrong Here?

Feb 18, 2010 5:04 PM

What's Wrong Here?

Feb 4, 2010 5:06 PM

View all What's Wrong Here?

product of the week

CAD Software

March 15, 2010

CAD Software

View all 2010 Products of the Week

Shocking Stats

54
More Industry Statistics

Recent Comments

More...




Professionals provide answers to your questions. Become an expert!


EC&M TV

Arlington CED1 Entrance Hoods

The Scoop Series CED Entrance Plates and Hoods are reversible, non-metallic, single and two-gang versions...

Southwire's 2009 Cable Innovation Road Show

Gain years worth of insight with Southwire’s 2009 Cable Innovation Road Show with Grounding Seminar!

George Brown College

Online Tech Training – Electronics, PLC, and Robotics programs at George Brown College.

 

Listen
Sizing Gen-Sets: Facts, Hints, and Good Judgment
Listen

The complexities of today’s commercial or industrial facility, with their equipment environment of linear and nonlinear loads, places a whole new light on sizing engine-generator sets.

Arc Mitigation - A Total System Approach
There’s no question the risk of arc flash hazards is real in the electrical industry. What many don’t always realize is the impact in business interruption from such events typically far outweighs the physical damage to equipment. View this On Demand Webinar!

Implementing an Industrial Ethernet Infrastructure that's Built to Last
This webinar explores the key benefits of implementing a robust complete, end-to-end Industrial Ethernet solution – from cabling and connectivity, to active components and associated hardware. View this On Demand Webinar!

resources

product info icon

product info

tradeshow icon

tradeshow

research icon

research

rss icon

rss

Browse Back Issues

Browse Back Issues