Code Quiz

Dec 13, 2007 12:07 PM, By Steven Owen

Q. In a large electrical room with numerous pieces of equipment rated at 1,200A or more, the question has arisen as to whether panic hardware is or is not required on all of the personnel doors. One personnel door is located 30 feet from the nearest edge of the switchgear, which is rated at 2,000A. The other personnel door is located 3 feet from the nearest edge of the motor control center, which is rated at 1,600A. There is also a roll-up door for moving equipment in and out of the room. Per the 2008 version of the NEC, which one of the following is the correct answer?

    1. All personnel doors must have panic hardware and open in the direction of egress. In this example, it would include both the personnel doors.
    2. All personnel and equipment doors must have panic hardware.
    3. All personnel doors located within 25 feet of electrical equipment rated 1,200A or greater must have panic hardware, and open in the direction of egress. In this example, it would only include the personnel door located within 3 feet of the motor control center.
    4. Section 110.26(C)(3) would not apply in this example because the width of the electrical equipment is not known. This section of the Code applies only to equipment that is rated 1,200A or greater, and more than 6 feet in width.

Answer: C

Section 110.26(C)(3) of the 2008 NEC has been revised. The revision does not require panic hardware on the personnel door(s) if the door(s) are located 25 feet or more from the nearest edge of electrical equipment rated 1,200A or greater. Equipment width is not an issue in this section.

Owen is the owner and president of National Code Seminars and the holder of master electrician certifications in 46 states. He can be reached at necexpert@aol.com.

Find More Code Quizzes »

Want to use this article? Click here for options!




Acceptable Use Policy
blog comments powered by Disqus

what's wrong here?

Whats Wrong Here?

Mar 11, 2010 12:54 PM

What's Wrong Here?

Feb 18, 2010 5:04 PM

What's Wrong Here?

Feb 4, 2010 5:06 PM

View all What's Wrong Here?

product of the week

CAD Software

March 15, 2010

CAD Software

View all 2010 Products of the Week

Shocking Stats

54
More Industry Statistics

Recent Comments

More...




Professionals provide answers to your questions. Become an expert!


EC&M TV

Arlington CED1 Entrance Hoods

The Scoop Series CED Entrance Plates and Hoods are reversible, non-metallic, single and two-gang versions...

Southwire's 2009 Cable Innovation Road Show

Gain years worth of insight with Southwire’s 2009 Cable Innovation Road Show with Grounding Seminar!

George Brown College

Online Tech Training – Electronics, PLC, and Robotics programs at George Brown College.

 

Listen
Sizing Gen-Sets: Facts, Hints, and Good Judgment
Listen

The complexities of today’s commercial or industrial facility, with their equipment environment of linear and nonlinear loads, places a whole new light on sizing engine-generator sets.

Arc Mitigation - A Total System Approach
There’s no question the risk of arc flash hazards is real in the electrical industry. What many don’t always realize is the impact in business interruption from such events typically far outweighs the physical damage to equipment. View this On Demand Webinar!

Implementing an Industrial Ethernet Infrastructure that's Built to Last
This webinar explores the key benefits of implementing a robust complete, end-to-end Industrial Ethernet solution – from cabling and connectivity, to active components and associated hardware. View this On Demand Webinar!

resources

product info icon

product info

tradeshow icon

tradeshow

research icon

research

rss icon

rss

Browse Back Issues

Browse Back Issues