Sep 24, 2009 1:06 PM, By Steven Owen

When installing wiring in escalators, moving walkways, platform lifts, stairway chairlift runways, machinery spaces, control spaces, or machine/control rooms (not including the traveling cables connecting the car, or counterweight and hoistway wiring), which of the following methods is not permitted?

    1. Rigid metal conduit, intermediate metal conduit, rigid nonmetallic conduit.
    2. Electrical nonmetallic tubing (ENT).
    3. Wireways.
    4. MC, MI or AC [unless otherwise permitted in 620.21(A) through (C)].

    Answer: B

    This answer is pretty straightforward. Electrical nonmetallic tubing (ENT) is not one of the approved wiring methods listed in 620.21 (Wiring Methods for Elevators, Dumbwaiters, Escalators, Moving Walks, Platform Lifts, and Stairway Chairlifts). ENT is a pliable raceway that can be bent by hand with a reasonable force, but without other assistance. In part, that is how this product type differs from nonmetallic (PVC) conduits of Art. 352.

    Owen is the owner and president of National Code Seminars and the holder of master electrician certifications in 46 states. He can be reached at necexpert@aol.com.

    Find More Code Quizzes »

    Want to use this article? Click here for options!




    Acceptable Use Policy
    blog comments powered by Disqus

    what's wrong here?

    What's Wrong Here?

    Feb 4, 2010 5:06 PM

    Whats Wrong Here?

    Jan 21, 2010 4:40 PM

    What's Wrong Here?

    Jan 7, 2010 12:47 PM

    View all What's Wrong Here?

    product of the week

    Enclosures

    February 8, 2010

    Enclosures

    View all 2010 Products of the Week

    Shocking Stats

    54
    More Industry Statistics

    Recent Comments

    More...




    Professionals provide answers to your questions. Become an expert!



    EC&M TV

    Arlington CED1 Entrance Hoods

    The Scoop Series CED Entrance Plates and Hoods are reversible, non-metallic, single and two-gang versions...

    Southwire's 2009 Cable Innovation Road Show

    Gain years worth of insight with Southwire’s 2009 Cable Innovation Road Show with Grounding Seminar!

    Listen
    Sizing Gen-Sets: Facts, Hints, and Good Judgment
    Listen

    The complexities of today’s commercial or industrial facility, with their equipment environment of linear and nonlinear loads, places a whole new light on sizing engine-generator sets.

    Arc Mitigation - A Total System Approach
    There’s no question the risk of arc flash hazards is real in the electrical industry. What many don’t always realize is the impact in business interruption from such events typically far outweighs the physical damage to equipment. View this On Demand Webinar!

    Implementing an Industrial Ethernet Infrastructure that's Built to Last
    This webinar explores the key benefits of implementing a robust complete, end-to-end Industrial Ethernet solution – from cabling and connectivity, to active components and associated hardware. View this On Demand Webinar!

    resources

    product info icon

    product info

    tradeshow icon

    tradeshow

    research icon

    research

    rss icon

    rss

    Browse Back Issues

    Browse Back Issues