Q. When does the NEC require a main breaker in a load center?

A. Each lighting and appliance branch-circuit panelboard must be protected on the supply side [408.16(A)]. The overcurrent protection device can be located within the panelboard, or the panelboard’s feeder overcurrent protection device could be used if its rating doesn't exceed the ampere rating of the panelboard [408.16(A) Ex.1].

Got a Code question for Mike? Send it to him at mike@mikeholt.com.


Commenting terms of use blog comments powered by Disqus

Want to use this article? Click here for options!

product of the week

Evaluation Software

December 1, 2008 9:59 AM

Honeywell Power Evaluation Software

View all 2008 Products of the Week

Recent Comments

Follow comments on ecmweb.com




Arc Flash Conferences   Code Change Conferences

Professionals provide answers to your questions.



Do you have any technical paper explaining IBC?

iGard Resistance Grounding Q&A BookletDownload the Resistance Grounding Q&A Booklet
I-Gard
EC&M TV

Retrofit 2-Gang TV Box(TM)

Arlington’s recessed two-gang TV BOX™ for old work allows you to mount LCD and plasma TVs, and other system components flush against the wall.

Listen
"Sizing Gen-Sets: Facts, Hints, and Good Judgment"
Listen
Sponsored By:

resources

product info icon

product info

tradeshow icon

tradeshow

research icon

research

rss icon

rss

Back to Top

Browse Back Issues

Browse Back Issues