ECM Buyers' Guide
  

Code Quandaries

Here are the latest short answers to questions posted on our Web site. In our discussion, we will cover topics from Secs. 90-2(b)(4), 250-2(a), 250-30(a)(1), 250-66(a), 800-11(a), and 810-18; and Art. 800 of the National Electrical Code (NEC).

Q. The NEC requires you to ground metal parts of the electrical system to the earth to limit high voltage imposed from lightning, line surges, or unintentional contact with higher voltage systems [Sec. 250-2(a)]. To accomplish this, you must install a conductive path from the metal parts of the electrical system to the earth. What is the largest size copper grounding electrode conductor required to bond the metal parts of the electrical system to a "made electrode," such as a ground rod? How does the size of the service affect the sizing of the grounding electrode conductor to a made electrode?

A. The size of the service has no effect on the sizing of the grounding electrode conductor to a made electrode because this conductor is not sized to carry fault current. As a result, the grounding electrode conductor from the grounded conductor to a "made electrode" is not required to be larger than No. 6 copper or No. 4 aluminum wire. You can find this requirement in Sec. 250-66(a).

Q. We place telephone service entrance cable in the same trench with the utility power cables to serve our residential telephone customers. This practice is in accordance with our company telephone engineering specifications. What are the NEC guidelines regarding "joint trench applications?"

A. NEC Sec. 90-2(b)(4) does not cover the installation of communications equipment under the exclusive control of communications utilities located outdoors. Therefore, it's not an NEC violation to install telephone cables in the same trench with service entrance cable. However, if the telephone wiring is not under the exclusive control of the communication utility, then Art. 800 requirements apply.

Unfortunately, there is no specific rule covering this subject! Sec. 800-11(a) requires separation by brick, concrete, tile partitions, or a suitable barrier for underground circuits entering buildings in a "raceway, handhole, or manhole."

Note: Sec. 810-18 requires you to separate underground "radio and television conductors" at least 12 in. from power circuit conductors.

Q. We recently had a contractor bond the neutral and grounds at both the transformer case and at the secondary disconnect. When asked about bonding at two separate locations, he said the transformer is the same as the power company's transformer, and the secondary disconnect is the same as the service entrance equipment. Is this correct?

A. No. You can only bond transformers (separately derived systems) at one location. You can make this connection at any point on the separately derived system from the source to the first system disconnecting means per Sec. 250-30(a)(1).

A new exception was added to this section of the Code that permits you to install a bonding jumper at both the source and the first disconnecting means, which does not establish a parallel path for the grounded circuit conductor. I recommend you use the neutral-to-ground bond at one location, either at the source or at the first system disconnecting means.

Find More Code Q&As »






Acceptable Use Policy
blog comments powered by Disqus

what's wrong here?

What's Wrong Here?

Feb 2, 2012 7:54 PM

What's Wrong Here?

Jan 19, 2012 4:06 PM

What's Wrong Here?

Jan 5, 2012 11:53 AM

View all What's Wrong Here?

product spotlight

Labeling tool

Feb 10, 2012 7:58 AM

Labeling tool

The Rhino 4200 labeling tool features one-touch “hot keys” that quickly create and format wire/cable wraps, flags, fixed-length labels and more...

View all 2012 Product Spotlights

Free Product Info

Our Product Information site is the ultimate online resource for products and services offered by Advertisers featured in our Magazine. This service is provided as a quick and easy way to request Product Information online. Get FREE product information now.

Recent Comments

More...


Social Media

More ways to stay informed...

follow us on twitter

Find us on Facebook

EC&M TV

Arlington CP9000

Arlington's new 9" diameter ceiling cover plate is the neatest way to cover unused "high hat" cans. With no tools needed, installation couldn't be faster!...

Arlington Gangable Boxes

Designed for new or retrofit applications, these snap-together gangable plastic boxes eliminate the need to construct a multiple-gang steel box out of several individual ones...

Understanding NEC Requirements for Solar Photovoltaic Systems
During this session, Mike Holt will address possible conflicts or confusing NEC requirements, provide tips on proper electrical installation techniques, and discuss the dangers related to improper installations. View this On Demand Webinar!



resources

product info icon

product info

tradeshow icon

tradeshow

research icon

research

industry links

industry links

rss icon

rss

Browse Back Issues

Browse Back Issues