Q. Our utility requires a nonfused disconnect upstream of the meter and service disconnect for certain services. Is this legal?

A. Yes, meter disconnect switches that have a short-circuit current rating (SCCR) equal to or more than the available short-circuit current can be installed ahead of the service disconnecting means. A meter disconnect switch must be capable of interrupting the load served [230.82(3)]. Electric utilities often require a meter disconnect switch for 277/480V services to enhance safety for utility personnel when they install or remove a meter.


Acceptable Use Policy
blog comments powered by Disqus

product of the week

Work gear

January 5, 2009 10:53 AM

DeWalt Work Gear

View all 2009 Products of the Week

Recent Comments

Follow comments on ecmweb.com



Professionals provide answers to your questions.



Do you have any technical paper explaining IBC?

iGard Resistance Grounding Q&A BookletDownload the Resistance Grounding Q&A Booklet
I-Gard



Arc Flash Conferences   Code Change Conferences
EC&M TV

Retrofit 2-Gang TV Box(TM)

Arlington’s recessed two-gang TV BOX™ for old work allows you to mount LCD and plasma TVs, and other system components flush against the wall.

Listen
"Sizing Gen-Sets: Facts, Hints, and Good Judgment"
Listen
Sponsored By:

resources

product info icon

product info

tradeshow icon

tradeshow

research icon

research

rss icon

rss

Back to Top

Browse Back Issues

Browse Back Issues