ECM Buyers' Guide
  

Code Calculations

Sep 23, 2004 11:21 AM, By Mike Holt

According to the U.S. Census Bureau, there are more than 3,500 recreational and vacation camps in this country. That's a lot of supply facility sites for recreational vehicles. Although the work may not be performed on a regular basis, do you know the rules for sizing services for these facilities? If not, read on and then test your skills by tackling our sample question.

Recreational vehicle parks are calculated according to the demand factor of Table 551.73. The total calculated load is based on:
• 2,400VA for each 20A supply facilities site
• 3,600VA for each 20A and 30A supply facilities site
• 9,600VA for each 50A, 120/240V supply facilities site

Ready for a quiz? A recreational vehicle park has 42 sites: three are rated 50A, 240/120V; 30 are rated 30/20A; and nine are rated 20A. What's the minimum feeder demand load for these sites?

A) 158kVA
B) 101kVA
C) 139kVA
D) 65kVA

Answer: As per the requirements of 551.71, 551.73(A), and Table 551.73, the correct answer is 65kVA. Note: A minimum of 70% of the sites must have a 30/20A facility (3,600VA per site). Find the answer as follows:

Step 1: Determine the total connected load.
3 sites at 50A = 3 x 9,600VA = 28,800VA
30 sites at 30A = 30 sites x 3,600VA = 108,000VA
9 sites at 20A = 9 x 2,400VA = 21,600VA
Total load = 28,800VA + 108,000VA + 21,600VA = 158,400VA

Step 2: Determine the demand factor per Table 551.73.
In this case, it's 41%.

Step 3: Determine the net computed demand load:
158,400VA x 0.41 = 64,944VA ÷ 1,000 = 65kVA

Want to use this article? Click here for options!



Acceptable Use Policy
blog comments powered by Disqus

what's wrong here?

What's Wrong Here?

Nov 5, 2009 11:50 AM

What's Wrong Here?

Oct 22, 2009 11:16 PM

What's Wrong Here?

Oct 8, 2009 3:32 PM

View all What's Wrong Here?

product of the week

Video camera scopes

November 16, 2009

Video camera scopes

View all 2009 Products of the Week

Recent Comments

More...


EC&M TV

Exterior Fixture Box for Brick or Stone

Installing a fixture box in a brick or stone wall just got easier with Arlington’s new adjustable depth box!

Southwire's 2009 Cable Innovation Road Show

Gain years worth of insight in only 2-1/2 hours with Southwire’s 2009 Cable Innovation Road Show with Grounding Seminar. The agenda is packed with valuable information that focuses on installation tips!

Listen
Sizing Gen-Sets: Facts, Hints, and Good Judgment
Listen

The complexities of today’s commercial or industrial facility, with their equipment environment of linear and nonlinear loads, places a whole new light on sizing engine-generator sets.

Arc Mitigation - A Total System Approach
There’s no question the risk of arc flash hazards is real in the electrical industry. What many don’t always realize is the impact in business interruption from such events typically far outweighs the physical damage to equipment. View this On Demand Webinar!

Implementing an Industrial Ethernet Infrastructure that's Built to Last
This webinar explores the key benefits of implementing a robust complete, end-to-end Industrial Ethernet solution – from cabling and connectivity, to active components and associated hardware. View this On Demand Webinar!

resources

product info icon

product info

tradeshow icon

tradeshow

research icon

research

rss icon

rss

Browse Back Issues

Browse Back Issues