According to the U.S. Census Bureau, there are more than 3,500 recreational and vacation camps in this country. That's a lot of supply facility sites for recreational vehicles. Although the work may not be performed on a regular basis, do you know the rules for sizing services for these facilities? If not, read on and then test your skills by tackling our sample question.

Recreational vehicle parks are calculated according to the demand factor of Table 551.73. The total calculated load is based on:
• 2,400VA for each 20A supply facilities site
• 3,600VA for each 20A and 30A supply facilities site
• 9,600VA for each 50A, 120/240V supply facilities site

Ready for a quiz? A recreational vehicle park has 42 sites: three are rated 50A, 240/120V; 30 are rated 30/20A; and nine are rated 20A. What's the minimum feeder demand load for these sites?

A) 158kVA
B) 101kVA
C) 139kVA
D) 65kVA

Answer: As per the requirements of 551.71, 551.73(A), and Table 551.73, the correct answer is 65kVA. Note: A minimum of 70% of the sites must have a 30/20A facility (3,600VA per site). Find the answer as follows:

Step 1: Determine the total connected load.
3 sites at 50A = 3 x 9,600VA = 28,800VA
30 sites at 30A = 30 sites x 3,600VA = 108,000VA
9 sites at 20A = 9 x 2,400VA = 21,600VA
Total load = 28,800VA + 108,000VA + 21,600VA = 158,400VA

Step 2: Determine the demand factor per Table 551.73.
In this case, it's 41%.

Step 3: Determine the net computed demand load:
158,400VA x 0.41 = 64,944VA ÷ 1,000 = 65kVA


Acceptable Use Policy
blog comments powered by Disqus

Want to use this article? Click here for options!

what's wrong here?

What's Wrong Here?

Jul 2, 2009 6:51 PM

What's Wrong Here?

Jun 18, 2009 4:01 PM

What's Wrong Here?

Jun 4, 2009 1:26 PM

View all What's Wrong Here?

Recent Comments

Follow comments on ecmweb.com

i-Gard contest
Here’s your chance to win $5000! All you have to do is submit a case history based on your or your client’s experience (positive or negative) in applying HRG technology to an existing or new power distribution system.
EC&M White Papers
Protecting Generators through Hybrid Grounding
The industry has recently become aware of the problem of severe generator damage due to stator ground faults. Two factors have been identified as contributors to this growing problem
EC&M TV

Retrofit 2-Gang TV Box(TM)

Arlington’s recessed two-gang TV BOX™ for old work allows you to mount LCD and plasma TVs, and other system components flush against the wall...

Hybrid Grounding - The industry has recently become aware of the problem of severe generator damage due to stator ground faults. Join us for this live webinar!

Arc Flash HazardThe 3 As of Arc Flash - Awareness, Analysis, Action

resources

product info icon

product info

tradeshow icon

tradeshow

research icon

research

rss icon

rss

Browse Back Issues

Browse Back Issues