Taking Care of Transformers, Part 3

The three categories of transformer testing 

 

Transformer maintenance consists mostly of testing, although it includes other activities (e.g., housekeeping-related). The three categories of transformer testing are:

1.    Acceptance. Normally, you perform acceptance tests following initial installation. The test results provide baseline maintenance data. But if a transformer has not operated for a while, it requires acceptance testing again. The normal definition of "a while" is three days or more, but you might use a shorter timeframe if conditions warrant (e.g., the sprinkler system operated).

2.    Routine. These are data collection activities, such as recording temperatures, and don’t require de-energization.

3.    Periodic. The complete menu of these tests requires a deep skill set, and thus they are typically outsourced to a testing firm.

In the next several parts of this series, we'll examine these further.

Discuss this Article 0

Post new comment
Sign In or register to use your Electrical Construction & Maintenance (EC&M) Magazine ID
(optional)

White Papers
EC&M Learning Center
Webinars
EC&M TV
Apr. 15, 2013
video

The Westex Difference

Learn what sets Westex apart from other flame resistant fabric manufacturers....More

Newsletter Signup

Connect With Us