Taking Care of Transformers, Part 2

Sept. 11, 2012
Your first step in forming an effective transformer maintenance plan (or evaluating the one you have) is to determine how critical each transformer is (e.g., on a scale of 1 to 5). 

Your first step in forming an effective transformer maintenance plan (or evaluating the one you have) is to determine how critical each transformer is (e.g., on a scale of 1 to 5). This allows you to allocate your limited maintenance resources.

Transformer failure risk factors vary by operating environment, so your next step is to carefully assess the environment of each transformer for issues such as heat, contaminants, power quality, load distribution, and access for maintainability. For each of these, assign a severity rating.

Your budget is limited, so you must make decisions that balance cost against loss. This means you gear your program to control the most severe risk factors for the most critical transformers. What’s left over can be allocated to the next level of criticality.

Voice your opinion!

To join the conversation, and become an exclusive member of EC&M, create an account today!

Sponsored Recommendations

Strut Comparison Chart

Conduit support systems are an integral part of construction infrastructure. Compare steel, aluminum and fiberglass strut support systems.

Electrical Conduit for Bridges Guide

Learn about electrical conduit for bridge projects.

Fiberglass Electrical Conduit Chemical Resistance Chart

This information is provided solely as a guide since it is impossible to anticipate all individual site conditions. For specific applications which are not covered in this guide...

Strut Corrosion Guide

Learn how Champion Strut™ benefits projects with corrosion resistance.