NEC in the Facility
If you have overhead service conductors, do they comply with the NEC, Art. 230, Part II? For example, they must be of sufficient capacity to handle the load. If you've added or upgraded service equipment, this may no longer be the case. While load diversity can prevent an immediate problem, a load usage change can produce an unpleasant surprise.
What about clearances? Are these conductors at least:
- 8 ft above the rooftops of buildings?
- 10 ft above grade at the service entrance?
- 18 ft above driveways and parking lots?
Service conductors must attach to buildings only with fittings identified for use with service conductors. If you can't visually inspect to determine if the fittings in your installation are correct and can't verify from invoices or other documents, then you need to replace those fittings.
If you have underground service conductors, then you obviously don't have overhead clearance requirements. The ampacity requirements still apply. Additionally, these must meet the requirements of 300.5 for protection against physical damage.
Want to use this article? Click here for options!
© 2012 Penton Business Media, Inc.
Latest Articles
EV charger tester
May 25, 2012 8:26 AM
CFL/LED dimmer
May 24, 2012 8:48 AM
Load bank
May 23, 2012 9:33 AM
Trending Articles
Acceptable Use Policy blog comments powered by Disqus
advertisement
what's wrong here?
What's Wrong Here?
May 10, 2012 12:44 PM
View all What's Wrong Here?
What's Wrong Here
Sponsored By:
product spotlight
EV charger tester
May 25, 2012 8:26 AM
The Electrician is portable tester that verifies critical power and safety requirements of electric vehicle (EV) chargers...
View all 2012 Product Spotlights
Free Product Info
Our Product Information site is the ultimate online resource for products and services offered by Advertisers featured in our Magazine. This service is provided as a quick and easy way to request Product Information online. Get FREE product information now.