Maintaining Your Service Entrance, Part 3
Nov 10, 2009 12:04 PM
Many tasks essential to proper maintenance of service equipment require de-energization. To perform those tasks, you must schedule an outage. Unfortunately, production departments can agree to only a limited outage window. Consequently, the work proceeds on a compressed schedule.
Don't underestimate the amount of this compression when planning the outage. Overly-optimistic job estimates combined with scope creep can easily result in too many tasks being attempted in too little time. People take dangerous shortcuts in response to the pressure.
For example, you can “save time” by eliminating a step or two in the tool count. A “100%” approach to the tool count takes time. But it provides a sure way to prevent energizing a bus bar that’s shorted to ground by a forgotten wrench.
The solution to the time crunch isn’t eliminating safety measures (e.g., tool count steps) or “working faster.” Furthermore, simply throwing more people at a job can actually slow progress.
So what’s the solution? Plan realistically what can be done within the limited time available, allowing for contingencies and cleanup.
To know what can realistically be done, conduct dry runs and walk-throughs. Bonus: These help you identify and address such issues as lighting, ventilation, temporary power, housekeeping, and safety problems ahead of time rather than during the outage window.
Want to use this article? Click here for options!
© 2010 Penton Business Media, Inc.
MRO Insider
Safety
Mar 9, 2010 12:46 PM
The best protection against arc blast is "don’t be there." This, however, isn't always possible. The next best precaution is...
NEC in the Facility
Mar 9, 2010 12:43 PM
Most facilities today have surge arresters on the building supply (service). These are typically bought on a budget mentality that results in a waste of the entire investment. It doesn't have to be that way...
Failed Repairs
Mar 9, 2010 12:42 PM
A repair that isn't done correctly is a failure waiting to happen. Some common errors include...
Electrical Troubleshooting Quiz
Mar 9, 2010 12:27 PM
A rash of motor failures has afflicted your plant. Your plant engineer read some application notes from the Web site of a test instrument manufacturer and subsequently used a power analyzer on the feeders of these motors...
Acceptable Use Policy blog comments powered by Disqus
advertisement
what's wrong here?
|
Whats Wrong Here?Mar 11, 2010 12:54 PM |
|
What's Wrong Here?Feb 18, 2010 5:04 PM |
|
What's Wrong Here?Feb 4, 2010 5:06 PM |
View all What's Wrong Here?
What's Wrong Here
Sponsored By:

Email