NEC in the Facility
Don't let a lack of existing service capacity force you to choose between either giving up expansion plans or taking the whole facility down so you can rip out the existing service and replace it with a larger one. The former won't please upper management, and the latter could turn into the kind of project you wish you'd never undertaken (it won't please upper management, either).
Fortunately, there's a third option.
The NEC provides four circumstances in which you can add a service:
- Special conditions. Offload that fire protection pump onto its own service (five other types of systems also qualify).
- Special occupancies. For example, a building is so large it requires more than one service.
- Capacity requirements. You'll need the electric utility and AHJ to agree.
- Different characteristics. There may be a reason, such as different voltages, to use different services.
Want to use this article? Click here for options!
© 2012 Penton Business Media, Inc.
Latest Articles
EV charger tester
May 25, 2012 8:26 AM
CFL/LED dimmer
May 24, 2012 8:48 AM
Load bank
May 23, 2012 9:33 AM
Trending Articles
Acceptable Use Policy blog comments powered by Disqus
advertisement
what's wrong here?
What's Wrong Here?
May 10, 2012 12:44 PM
View all What's Wrong Here?
What's Wrong Here
Sponsored By:
product spotlight
EV charger tester
May 25, 2012 8:26 AM
The Electrician is portable tester that verifies critical power and safety requirements of electric vehicle (EV) chargers...
View all 2012 Product Spotlights
Free Product Info
Our Product Information site is the ultimate online resource for products and services offered by Advertisers featured in our Magazine. This service is provided as a quick and easy way to request Product Information online. Get FREE product information now.