Understanding the Estimating Process — Part 9 of 12

Sept. 21, 2011
Getting closer to your proposal

Last month in “Estimating 101,” we discussed methods to check your take-off, review quotes, and apply direct job expenses to your bid. Now that you’ve determined your take-off is accurate and applied the necessary costs, let’s talk about other labor items to consider.

Depending on the size of the project you are bidding, you may have to carry money for a project manager, whose responsibility will be to ensure that the job is built to what was carried in the bid and/or negotiated upon award. Oftentimes, the field labor force, for example, will have no idea that special provisions were negotiated with the owner for certain things, such as the use of aluminum feeders (if allowable by local code) or open fire alarm cable. The project manager will communicate this to the job foreman, another labor component you should carry — again depending on job size. For very large or complex projects, you may have to carry more than one foreman. In union environments, the labor superintendant’s and/or a steward’s salary will probably be considered part of the company overhead, which we will get to a little later. Some larger companies also carry money for the estimator or clerical staff, but not necessarily in this fragile economy!

Technically, for any building more than four stories tall, the labor escalation rate is 1% to 2% per floor, which means that any item that is installed on the 20th floor, for example, will take longer to install than one on the first floor. How is that possible? Let’s not forget that a labor unit is comprised of the actual installation time, plus time for material procurement, coffee breaks, and actually getting to the area of work. So presumably, it is going to take longer to get to the 20th floor than the first floor, including not only waiting for the man lift but also transporting the appropriate material to the work area from the staging area.

In this competitive bid market, I realize that if you carry everything that I talk about, you may never be awarded a job. However, it is the estimator’s responsibility to identify all the costs. Then, upon review of the estimate and bid, items can be strategically cut to get closer to a more competitive number. At this point, decisions to cut items become strategic, but you have to know your complete costs before your strategy comes into play.

That leads me to the last items we need to address in order to put a number on our job: overhead and profit. Some companies bid their projects with a “fully burdened rate,” meaning the labor rate that they use to bid a project already includes a specified overhead amount in the hourly rate. Other companies apply their overhead rate as a percentage as a line item in their bid. Whichever option you choose, you should know what your overhead percentage is and carry it on every job. If you don’t know your overhead percentage, talk to your accountant. If you recall, I suggested in a previous installment of this series that you should make friends with your accountant, so you will already have this information. You simply cannot bid a job without covering all your costs, unless you want to risk the exposure of losing money on the project, if awarded.

Finally, profit is a beautiful thing. However, in this gloomy economy, most estimators I know put in very little (2% to 5%) for profit — and for good reason. The market right now is just too darn competitive. This is where knowing your market, your customer, and your competition will guide you to success. Only you can decide what will give you the magic number to get a scope review and eventual project award. Look at past bids and completed projects, review your numbers, and see if you can get an advantage somewhere.

Next month, we will discuss your bid price and putting together a proposal (scope) letter to accurately describe what is included in your price. This is the final — and one of the most important — step in submitting your price to the general contractor. Don’t miss it!

Candels is president of Candels Consulting, an electrical estimating consulting firm in New York City. She can be reached at [email protected].

About the Author

Linda Candels

Voice your opinion!

To join the conversation, and become an exclusive member of EC&M, create an account today!

Sponsored Recommendations

Electrical Conduit Comparison Chart

CHAMPION FIBERGLASS electrical conduit is a lightweight, durable option that provides lasting savings when compared to other materials. Compare electrical conduit types including...

Fiberglass Electrical Conduit Chemical Resistance Chart

This information is provided solely as a guide since it is impossible to anticipate all individual site conditions. For specific applications which are not covered in this guide...

Considerations for Direct Burial Conduit

Installation type plays a key role in the type of conduit selected for electrical systems in industrial construction projects. Above ground, below ground, direct buried, encased...

How to Calculate Labor Costs

Most important to accurately estimating labor costs is knowing the approximate hours required for project completion. Learn how to calculate electrical labor cost.