Anatomy of a Wind Energy Project

Jan. 1, 2009
A coal-fired or nuclear plant can take a decade to build, but the construction of a wind farm can be completed in six months to a year. Here is a step-by-step look at the construction of a wind farm from the groundbreaking through power generation. Step 1: The electrical contractors typically win contracts through a competitive bid process. Once on site, they wire job-site trailers, order materials,

A coal-fired or nuclear plant can take a decade to build, but the construction of a wind farm can be completed in six months to a year. Here is a step-by-step look at the construction of a wind farm from the groundbreaking through power generation.

Step 1: The electrical contractors typically win contracts through a competitive bid process. Once on site, they wire job-site trailers, order materials, plan the work, create a schedule and hire workers.

Step 2: Once the developer and design team have identified the site for the turbines, the civil contractors build roads leading into the site, and the electricians begin digging trenches and burying cables for the underground collection system. The fiber-optic, ground, and SCADA system cables connect all the turbines to a central brain in the middle of a substation.

Step 3: The electricians work with the other trades to build the foundations for the wind turbines.

Step 4: The construction crew lifts the tower in three different phases, and the electricians and technicians connect each section electrically and mechanically. The electricians drop the control wiring or fiber-optic cables down the side of the tower through a cable tray.

Step 5: Once they have completed the wiring of the turbines and connected them to the substation, the utility then interconnects the substation with the grid.

Step 6: The developer tests the turbines, and the turbines begin generating electricity. At that point, the electricians turn the project over to the wind technicians, who are responsible for operating and maintaining the wind turbines.

About the Author

Amy Fischbach

Voice your opinion!

To join the conversation, and become an exclusive member of EC&M, create an account today!

Sponsored Recommendations

How to Calculate Labor Costs

Most important to accurately estimating labor costs is knowing the approximate hours required for project completion. Learn how to calculate electrical labor cost.

Champion Strut Catalog

Champion Fiberglass is the most advanced manufacturing facility of fiberglass conduit, fiberglass bridge drain and fiberglass strut systems in the world. Its well-trained and ...

8 Types of Electrical Conduit and Their Uses

Electrical conduit is a tube or raceway used to house and protect electrical wires within a building or structure. From data centers to underground subways to ports and bridges...

Xpress Elbows Guide for Industrial Construction

Learn how to get expedited elbows shipped within 2 days.