Heller Electric Co. Finishes Electric Install for Presidential Inauguration

Jan. 9, 2013
Heller Electric Co. recently finished work on three separate structures for the Presidential Inauguration ceremony: the Presidential Reviewing Stand, Media Stand, and Mayoral Parade Reviewing Stand. An average of nine electricians worked 10-hour days, up to seven days a week to ensure it was completed by January 7.

This year marks the 11th consecutive time Heller Electric Co., Inc. has completed electric work for the Presidential Inauguration. This year's ceremony is scheduled for January 21.

Work on the 57th Presidential Inauguration began almost immediately after the election. Electrical Alliance contractor Heller Electric began electric installation on three separate structures for the ceremony: the Presidential Reviewing Stand, Media Stand, and Mayoral Parade Reviewing Stand the week before Thanksgiving. Since then, an average of nine electricians worked 10-hour days, up to seven days a week to ensure it was completed by January 7.

Heller installed 600A in the Presidential Reviewing Stand, where President Obama and his family will watch the parade, for lighting and heating the entire stand and bulletproof enclosure. The three-story Media Stand is powered by 800A that supply approximately 192 electric outlets for the worldwide media in attendance to utilize. Finally, Heller completed the heating and lighting work for the Mayoral Parade Stand that will hold the mayor and all Washington, D.C., government and guests.

“It is a bit challenging because of the definitive end and start date, ordering of custom materials, and allotment of only 10 people to work on the project because of security, but our team thrives on fast-paced jobs and we feel honored to work on such a prestigious job,” says Michael Ritchey, Heller Electric’s president.

With the inauguration, the electric work doesn’t end on the finish date. Four Heller Electric workers will man each structure and the materials trailer on the day of the ceremony to ensure all operations run smoothly.

“The Inaugural Stands have been a huge part of our history since 1973, when we were selected to light President Nixon’s second term inauguration," says Brian J. Heller, Heller’s executive VP. "Each inaugural project brings us not only new challenges, but stories and a tremendous sense of pride among all of our employees who work tirelessly to complete the projects on time. We look forward to the opportunity every four years and proudly celebrate our ability to participate in such a historical event.”

 

Voice your opinion!

To join the conversation, and become an exclusive member of EC&M, create an account today!

Sponsored Recommendations

Strut Comparison Chart

Conduit support systems are an integral part of construction infrastructure. Compare steel, aluminum and fiberglass strut support systems.

Electrical Conduit for Bridges Guide

Learn about electrical conduit for bridge projects.

Xpress Elbows Guide for Industrial Construction

Learn how to get expedited elbows shipped within 2 days.

8 Types of Electrical Conduit and Their Uses

Electrical conduit is a tube or raceway used to house and protect electrical wires within a building or structure. From data centers to underground subways to ports and bridges...