Negotiating a Force Majeure Clause

Nov. 1, 2005
When prices of construction materials spike, are specialty contractors entitled to a price adjustment to fixed-price contracts? According to the American Subcontractors Association (ASA) white paper, Force Majeure, the answer is no. Judges rarely rule in favor of an or unforeseeable event that prevents the contractor from performing work at the agreed-upon price. Instead, the judge will most likely

When prices of construction materials spike, are specialty contractors entitled to a price adjustment to fixed-price contracts? According to the American Subcontractors Association (ASA) white paper, “Force Majeure,” the answer is no. Judges rarely rule in favor of an “impracticability” or unforeseeable event that prevents the contractor from performing work at the agreed-upon price. Instead, the judge will most likely see the price spike as a risk inherent to the construction business. Therefore, the ASA advises specialty contractors to negotiate a force majeure clause in their contracts, giving them more rights than the legal doctrine of impracticability. ASA advises contractors to keep the following guidelines in mind when negotiating a force majeure clause:

Be specific. The clause should contain language to explicitly rebut the legal argument that price adjustments can only be made when work is “impracticable.”

Use measurable terms. The clause should be worded in a way that uses specific measurable conditions for an adjustment — such as “a material price increase of 20%.”

Be original. Most industry model documents for fixed-price contracts don't give subcontractors the right to equitable price adjustments. Modify standard documents to fit your specific needs.

Don't limit yourself. Many clauses limit the specialty contractor's adjustment to an extension of time but don't mention or deny price adjustments.

Voice your opinion!

To join the conversation, and become an exclusive member of EC&M, create an account today!

Sponsored Recommendations

Electrical Conduit Comparison Chart

CHAMPION FIBERGLASS electrical conduit is a lightweight, durable option that provides lasting savings when compared to other materials. Compare electrical conduit types including...

Fiberglass Electrical Conduit Chemical Resistance Chart

This information is provided solely as a guide since it is impossible to anticipate all individual site conditions. For specific applications which are not covered in this guide...

Considerations for Direct Burial Conduit

Installation type plays a key role in the type of conduit selected for electrical systems in industrial construction projects. Above ground, below ground, direct buried, encased...

How to Calculate Labor Costs

Most important to accurately estimating labor costs is knowing the approximate hours required for project completion. Learn how to calculate electrical labor cost.