The Basics of Reducing Touch Potential

April 1, 2001
Remove voltage on metal parts of an electrical system to protect against lethal shock. Here's a true or false question for you. Connecting metal parts of a 120V electrical system to a ground rod removes dangerous voltage imposed on the system from a line-to-ground fault by opening the overcurrent protection device (OCPD). If you answered you're wrong. To see why, let's review three fundamentals: Electrons

Remove voltage on metal parts of an electrical system to protect against lethal shock.

Here's a “true or false” question for you. “Connecting metal parts of a 120V electrical system to a ground rod removes dangerous voltage imposed on the system from a line-to-ground fault by opening the overcurrent protection device (OCPD).” If you answered “true,” you're wrong. To see why, let's review three fundamentals:

  1. Electrons leaving the power supply are attempting to return to the source. They are not trying to go to ground.

  2. The time it takes for an OCPD to open is inversely proportional to the magnitude of the fault current. The greater the ground-fault current, the less time it takes for the device to open.

  3. To protect against lethal shock, you must remove unsafe voltage on metal parts of the electrical system and the building. Do this by opening the circuit's OCPD in less than 1 sec.

To open the device in less than one second, be sure the fault current returning to the source must quickly rise to about 6× (fast-acting fuses) to 10× (other devices) the rating of the circuit OCPD.

Note: A GFCI protection device is not an OCPD. By design, it opens the circuit where the fault is as little as 5mA.

To remove dangerous voltage in less than 1 sec, make sure the fault current path is permanent and electrically continuous, capable of safely carrying the maximum fault likely to be imposed on it, and has a low impedance to allow the operation of overcurrent devices [Secs. 110-10 and 250-2(d)]. You create a low-impedance path when you bond together the metal parts of the electrical system [Sec. 250-90] and bond them to the power supply system grounded (neutral) conductor. Sec. 250-24 requires this operation for service equipment, while Sec. 250-30(b) calls for bonding for separately derived systems.

Naturally, the earth cannot be the intended return path to clear a fault because its high resistance (one billion times that of copper, per IEEE Std. 142 Sec. 2.2.8) will only allow a few (1 to 10) amperes to flow back to the source [Secs. 250-2(d) and 250-54].

You should ground power supply systems to the earth for two reasons. First, it prevents the destruction of electrical components from lightning, and it stabilizes the system voltage during normal operation (Sec. 250-28).

About the Author

Mike Holt

Mike Holt is the owner of Mike Holt Enterprises (www.MikeHolt.com), one of the largest electrical publishers in the United States. He earned a master's degree in the Business Administration Program (MBA) from the University of Miami. He earned his reputation as a National Electrical Code (NEC) expert by working his way up through the electrical trade. Formally a construction editor for two different trade publications, Mike started his career as an apprentice electrician and eventually became a master electrician, an electrical inspector, a contractor, and an educator. Mike has taught more than 1,000 classes on 30 different electrical-related subjects — ranging from alarm installations to exam preparation and voltage drop calculations. He continues to produce seminars, videos, books, and online training for the trade as well as contribute monthly Code content to EC&M magazine.

Voice your opinion!

To join the conversation, and become an exclusive member of EC&M, create an account today!

Sponsored Recommendations

Electrical Conduit Comparison Chart

CHAMPION FIBERGLASS electrical conduit is a lightweight, durable option that provides lasting savings when compared to other materials. Compare electrical conduit types including...

Don't Let Burn-Through Threaten Another Data Center or Utility Project

Get the No Burn-Through Elbow eGuide to learn many reasons why Champion Fiberglass elbows will enhance your data center and utility projects today.

Considerations for Direct Burial Conduit

Installation type plays a key role in the type of conduit selected for electrical systems in industrial construction projects. Above ground, below ground, direct buried, encased...

How to Calculate Labor Costs

Most important to accurately estimating labor costs is knowing the approximate hours required for project completion. Learn how to calculate electrical labor cost.