Anatomy of a Wind Energy Project

A coal-fired or nuclear plant can take a decade to build, but the construction of a wind farm can be completed in six months to a year. Here is a step-by-step look at the construction of a wind farm from the groundbreaking through power generation.

Step 1: The electrical contractors typically win contracts through a competitive bid process. Once on site, they wire job-site trailers, order materials, plan the work, create a schedule and hire workers.

Step 2: Once the developer and design team have identified the site for the turbines, the civil contractors build roads leading into the site, and the electricians begin digging trenches and burying cables for the underground collection system. The fiber-optic, ground, and SCADA system cables connect all the turbines to a central brain in the middle of a substation.

Step 3: The electricians work with the other trades to build the foundations for the wind turbines.

Step 4: The construction crew lifts the tower in three different phases, and the electricians and technicians connect each section electrically and mechanically. The electricians drop the control wiring or fiber-optic cables down the side of the tower through a cable tray.

Step 5: Once they have completed the wiring of the turbines and connected them to the substation, the utility then interconnects the substation with the grid.

Step 6: The developer tests the turbines, and the turbines begin generating electricity. At that point, the electricians turn the project over to the wind technicians, who are responsible for operating and maintaining the wind turbines.


Want to use this article? Click here for options!





Acceptable Use Policy
blog comments powered by Disqus

what's wrong here?

View all What's Wrong Here?

Free Product Info

Our Product Information site is the ultimate online resource for products and services offered by Advertisers featured in our Magazine. This service is provided as a quick and easy way to request Product Information online. Get FREE product information now.

Case Studies

More...

Recent Comments

More...


Social Media

More ways to stay informed...

follow us on twitter

Find us on Facebook

EC&M Whitepaper

Arc Mitigation –A Three-Step Approach

Did you know that an arc-flash incident hospitalizes 5-7 workers per day in North America, severely impacting processes and profitability with lost production? Download This Sponsored Whitepaper Today!

What's New in Residential Cabling?
Date: Wednesday, May 30, 2012
Time: 2:00pm ET


In this The Home Depot sponsored Low Voltage Webinar, Ron Kipper RCDD / NTS will discuss the need for compression style coaxial connectors and the migration of the entire CATV, Satellite and Audio / Video industry to them. Register Today!

Grounding Versus Bonding
Date: Thursday, May 24, 2012
Time: 2:30pm ET


In this 60-minute FREE webinar, Mike Holt of Mike Holt Enterprises, Inc. will explain the purpose of grounding and bonding as related to the most current requirements set forth in the 2011 NEC. Register Today!

resources

product info icon

product info

tradeshow icon

tradeshow

research icon

research

industry links

industry links

rss icon

rss

Browse Back Issues

Browse Back Issues