The Secret to Short-Interval Scheduling

First and foremost, the daily schedule is what needs to be done today, tomorrow, or the day after tomorrow (click here to see Fig. 3). Some of these tasks may be future tasks that the project plan does not have scheduled until later in the job; however, if the foreman has an opportunity to flatten the manpower loading curve by pulling some tasks ahead, he definitely should have the freedom to do so.

The project manager should make sure to review the task completion shown in SIS against the project schedule, and invoice ahead of schedule for work completed early. If future tasks have been scheduled early by the foreman, the project manager can reference the three-week look ahead and schedule more tasks accordingly. He can also add any other project planned-schedule tasks to his three-day schedule.

To create the SIS from scratch, the project managers, department managers, and the owners should start in the field. Start with asking your foremen what tasks they are going to complete each day for the next three days, who is going to work on them, and the scheduled time for the activity. Once the data is collected, it needs to be ranked and plotted to identify the obstacles foremen are facing.

Daneshgari is president and CEO and Moore is an associate implementer with MCA, Inc., Flint, Mich. They can be reached at perry@mca.net.


Want to use this article? Click here for options!





Acceptable Use Policy
blog comments powered by Disqus

what's wrong here?

What's Wrong Here?

Feb 2, 2012 7:54 PM

What's Wrong Here?

Jan 19, 2012 4:06 PM

What's Wrong Here?

Jan 5, 2012 11:53 AM

View all What's Wrong Here?

product spotlight

Labeling tool

Feb 10, 2012 7:58 AM

Labeling tool

The Rhino 4200 labeling tool features one-touch “hot keys” that quickly create and format wire/cable wraps, flags, fixed-length labels and more...

View all 2012 Product Spotlights

Free Product Info

Our Product Information site is the ultimate online resource for products and services offered by Advertisers featured in our Magazine. This service is provided as a quick and easy way to request Product Information online. Get FREE product information now.

Recent Comments

More...


Social Media

More ways to stay informed...

follow us on twitter

Find us on Facebook

EC&M TV

Arlington CP9000

Arlington's new 9" diameter ceiling cover plate is the neatest way to cover unused "high hat" cans. With no tools needed, installation couldn't be faster!...

Arlington Gangable Boxes

Designed for new or retrofit applications, these snap-together gangable plastic boxes eliminate the need to construct a multiple-gang steel box out of several individual ones...

Understanding NEC Requirements for Solar Photovoltaic Systems
During this session, Mike Holt will address possible conflicts or confusing NEC requirements, provide tips on proper electrical installation techniques, and discuss the dangers related to improper installations. View this On Demand Webinar!



resources

product info icon

product info

tradeshow icon

tradeshow

research icon

research

industry links

industry links

rss icon

rss

Browse Back Issues

Browse Back Issues