Historic St. Louis Opera House Shines Once More

Electrical contractor installs new electrical distribution system, lighting system, fire alarm system, and theatrical lighting system

Situated in downtown St. Louis, the Peabody Opera House is a 3,500-seat historic theater that has hosted the likes of Frank Sinatra, Ray Charles, and the Rolling Stones. The Art Deco building, formerly known as the Kiel Opera House, was originally constructed in 1934 and operated continuously until it closed in 1991. Thanks to a recent $78.7-million restoration project, the Peabody Opera House has been returned to its former glory and is once again a popular performance attraction.

“One of the major updates to the structure was a $6.5-million state-of-the-art electrical system,” says Mike Murphy, vice president of operations for Fenton, Mo.-headquartered Kaiser Electric, the electrical contractor that installed not only the building’s new electrical distribution system, but also a general lighting system, fire alarm system, and an estimated $1.3 million theatrical lighting system.

“The facility contains a main theater, four smaller venues, and numerous other spaces — all of which had to be tied to a central lighting control and dimming system that could be controlled or managed from multiple places throughout the facility,” explains Kaiser Electric President Steve Giacin.

According to Giacin, this proved challenging, because the historical integrity of the building, such as original plaster walls and moldings, had to be maintained while modernizing the electrical systems to meet present-day Code requirements.

“We had to get creative when working in the areas of historical significance, especially when it came to the fire alarm installation,” notes Murphy. “Sometimes that meant having to go up or down a floor or two.”

Preserving the building’s historic facets also dictated what types of energy-saving electrical features could be used.

“In the front of house and other public areas, we kept as many of the original luminaires as possible, which meant we had to stay with incandescent lamps,” Murphy says. “But behind the scenes, all the lamps have been changed to T5 or T8 fluorescents, or LEDs. We also installed occupancy sensors throughout the entire opera house, including the restrooms.”

One of the biggest energy savings resulted from removing the old dimming system and replacing it with a new one, says Murphy.

“The original system was located in the main theater and measured approximately the size of a small delivery truck,” he notes. “You don’t see many of those anymore.”

Furthermore, Kaiser Electric installed an outdoor back-up generator for egress lighting and the elevators. The contractor also assisted in the design and installation of LED color-shifting light fixtures in the large center dome located in the main theater.

“Installing the lighting in the dome was very difficult,” says Giacin. “Some of the fixtures had to be inserted, secured, and wired through handholes that were approximately 6 in. by 6 in. and located 2 ft to 3 ft apart.”

Despite the project’s unique challenges, the electrical installation, which began in June 2010, finished on schedule this past August and within budget. At peak construction, Kaiser Electric employed up to 31 electricians on the Peabody Opera House Project.


Want to use this article? Click here for options!





Acceptable Use Policy
blog comments powered by Disqus

what's wrong here?

What's Wrong Here?

May 10, 2012 12:44 PM

What's Wrong Here?

Apr 19, 2012 10:09 AM

What's Wrong Here?

Apr 5, 2012 2:27 PM

View all What's Wrong Here?

product spotlight

LED replacement lamp

May 22, 2012 8:12 AM

LED replacement lamp

The Array LED BR30 replacement lamp features an enhanced dimming circuit and the company’s second-generation Selective Heat Sink Technology...

View all 2012 Product Spotlights

Free Product Info

Our Product Information site is the ultimate online resource for products and services offered by Advertisers featured in our Magazine. This service is provided as a quick and easy way to request Product Information online. Get FREE product information now.

Recent Comments

More...


Social Media

More ways to stay informed...

follow us on twitter

Find us on Facebook

EC&M Whitepaper

Arc Mitigation –A Three-Step Approach

Did you know that an arc-flash incident hospitalizes 5-7 workers per day in North America, severely impacting processes and profitability with lost production? Download This Sponsored Whitepaper Today!

What's New in Residential Cabling?
Date: Wednesday, May 30, 2012
Time: 2:00pm ET


In this The Home Depot sponsored Low Voltage Webinar, Ron Kipper RCDD / NTS will discuss the need for compression style coaxial connectors and the migration of the entire CATV, Satellite and Audio / Video industry to them. Register Today!

Grounding Versus Bonding
Date: Thursday, May 24, 2012
Time: 2:30pm ET


In this 60-minute FREE webinar, Mike Holt of Mike Holt Enterprises, Inc. will explain the purpose of grounding and bonding as related to the most current requirements set forth in the 2011 NEC. Register Today!

resources

product info icon

product info

tradeshow icon

tradeshow

research icon

research

industry links

industry links

rss icon

rss

Browse Back Issues

Browse Back Issues