Installation and operation of optional standby systems

April 23, 2004
With last year’s blackout still lingering on the minds of many, the use of optional standby power systems is worth a closer look.

















With last year’s blackout still lingering on the minds of many, the use of optional standby power systems is worth a closer look. Art. 702 of the 2002 NEC covers the installation and operation of optional standby systems that are permanently installed in their entirety or those that are arranged for connection to a premises wiring system from a portable alternate power supply.


The scope of Art. 702 was changed for the 2002 issue of the Code to clarify that it applies to portable generators, which are commonly used for telecommunications facilities, water and wastewater pump stations, as well as to provide backup power to homes and offices. In addition, the sections of this article that deal with transfer equipment and portable generator grounding were also revised.

Transfer equipment – A new sentence was added to 702.6, which calls for a transfer switch to be installed whenever a fixed or portable standby generator is connected to a premises wiring system.

Portable generator grounding – A new section (702.10) was also added for grounding portable generators, which reads as follows:

“(A) Separately Derived Systems. If the transfer switch for a portable generator switches the grounded (neutral) conductor (separately derived system) then the portable generator must be grounded in accordance with 250.30.

“(B) Nonseparately Derived System. If the transfer switch for a portable generator does not switch the grounded (neutral) conductor, then the generator’s equipment grounding conductor must be bonded to the system grounding electrode.”

Section (A) means that the neutral of the portable generator must be bonded to the generator case and grounding electrode in accordance with the requirements of 250.30 (Fig. 1).

Section (B) means that the grounded (neutral) conductors of the generator must not be bonded to the case [250.142], but does require the case to be bonded to a system grounding electrode. The grounding electrode system for the building can be used for this purpose. Effectively, this rule is merely repeating the grounding requirements noted in Article 250 (Fig. 2).

About the Author

Mike Holt

Mike Holt is the owner of Mike Holt Enterprises (www.MikeHolt.com), one of the largest electrical publishers in the United States. He earned a master's degree in the Business Administration Program (MBA) from the University of Miami. He earned his reputation as a National Electrical Code (NEC) expert by working his way up through the electrical trade. Formally a construction editor for two different trade publications, Mike started his career as an apprentice electrician and eventually became a master electrician, an electrical inspector, a contractor, and an educator. Mike has taught more than 1,000 classes on 30 different electrical-related subjects — ranging from alarm installations to exam preparation and voltage drop calculations. He continues to produce seminars, videos, books, and online training for the trade as well as contribute monthly Code content to EC&M magazine.

Voice your opinion!

To join the conversation, and become an exclusive member of EC&M, create an account today!

Sponsored Recommendations

Electrical Conduit Comparison Chart

CHAMPION FIBERGLASS electrical conduit is a lightweight, durable option that provides lasting savings when compared to other materials. Compare electrical conduit types including...

Fiberglass Electrical Conduit Chemical Resistance Chart

This information is provided solely as a guide since it is impossible to anticipate all individual site conditions. For specific applications which are not covered in this guide...

Considerations for Direct Burial Conduit

Installation type plays a key role in the type of conduit selected for electrical systems in industrial construction projects. Above ground, below ground, direct buried, encased...

How to Calculate Labor Costs

Most important to accurately estimating labor costs is knowing the approximate hours required for project completion. Learn how to calculate electrical labor cost.