Don't get me started on unit equipment

Sept. 1, 2001
Section 700-12(e) requires unit equipment to be permanently fixed in place (i.e., not portable) and all wiring to each unit to be installed in accordance with the requirements of any of the wiring methods in Chapter 3. A flexible cord and plug connection is permitted, provided that the cord does not exceed 3 ft (914 mm) in length. The branch circuit feeding the unit equipment is required to be the

Section 700-12(e) requires unit equipment to be permanently fixed in place (i.e., not portable) and all wiring to each unit to be installed in accordance with the requirements of any of the wiring methods in Chapter 3. A flexible cord and plug connection is permitted, provided that the cord does not exceed 3 ft (914 mm) in length.

The branch circuit feeding the unit equipment is required to be the same branch circuit as that serving the normal lighting in the area, and connected ahead of any local switches. The branch circuit that feeds unit equipment must be clearly identified at the distribution panel.

Emergency illumination fixtures that obtain power from the unit equipment and are not part of the unit equipment must be wired to the unit equipment as required by Section 700-9 and by one of the wiring methods of Chapter 3.

About the Author

Joseph A. Tedesco

Voice your opinion!

To join the conversation, and become an exclusive member of EC&M, create an account today!

Sponsored Recommendations

How to Calculate Labor Costs

Most important to accurately estimating labor costs is knowing the approximate hours required for project completion. Learn how to calculate electrical labor cost.

Strut Comparison Chart

Conduit support systems are an integral part of construction infrastructure. Compare steel, aluminum and fiberglass strut support systems.

NECA Manual of Labor Rates Chart

See how Champion Fiberglass compares to PVC, GRC and PVC-coated steel in installation.

Electrical Conduit for Bridges Guide

Learn about electrical conduit for bridge projects.