Building a Data Center in Double Time

When Technology Site Planners (Tech Site) was faced with timeline, budget, and engineering challenges in designing, building, and commissioning a new data center’s on-site power system, the firm knew that meeting load capacity, power reliability, and availability requirements would not be an easy task. Because the client’s existing data center was already operating over capacity, to characterize the project as a rush job would be an understatement. Located near Cincinnati, Tech Site’s client required 4,000 sq ft of the data center be designed and built from the “ground up” within a warehouse and be fully operational in six to seven months — about half the time typically required for this type of project.

Tech Site suggested a design that could be doubled in size to 8,000 sq ft to accommodate further growth, modifications, and equipment additions. To be a complete success, however, they had to achieve layered redundancy to comply with the client’s high operational standards. Turning to Emerson Network Power for guidance on the power transfer design, Tech Site and the client decided the best course of action was a flexible design that could be modified and finalized while initial construction was underway. Essentially, some of the engineering and project management would be done "on the fly."

The project included redesigning the facility-side feed from the electric utility source, which comprises a single substation, roadside utility vault, and utility transformer. A new, pad-mounted 2,500kVA transformer also was installed. Inside the building, electric utility power feeds a switchboard that distributes power to two main closed transition ASCO transfer switches through separate breakers, each of which supplies power to the “normal” side of one transfer switch. These transfer switches establish a dual bus power feed arrangement to provide reliable, redundant power to the data center.

A 1,250kVA / 1,000kW generator feeds a switchboard that also distributes power to the two main transfer switches. The distribution switchboards keep power flowing through the uninterruptible power supplies to 75 server racks that manage information for national and international customers. Power also is supplied to four command center office units: a “War Room,” print room, build room, and the data center command and control room.

A 230A secondary ASCO transfer switch directs power from both busses to lighting panels and generator-backed receptacles. In addition, each computer room air conditioner unit is powered by a dedicated transfer switch supplied from both of the dual bus power feeds.

In the end, Tech Site pulled off an incredible accomplishment by completing the project on time and within budget. The result helps ensure reliable, scalable power to the data center.


Want to use this article? Click here for options!





Acceptable Use Policy
blog comments powered by Disqus

what's wrong here?

What's Wrong Here?

May 10, 2012 12:44 PM

What's Wrong Here?

Apr 19, 2012 10:09 AM

What's Wrong Here?

Apr 5, 2012 2:27 PM

View all What's Wrong Here?

product spotlight

Garage/utility lamp

May 16, 2012 9:26 AM

Garage/utility lamp

A suitable replacement for existing high-intensity discharge (HID) or high-pressure sodium (HPS) lamps, the 52W LED-8025 garage/utility lamp is designed for low-bay applications ...

View all 2012 Product Spotlights

Free Product Info

Our Product Information site is the ultimate online resource for products and services offered by Advertisers featured in our Magazine. This service is provided as a quick and easy way to request Product Information online. Get FREE product information now.

Recent Comments

More...


Social Media

More ways to stay informed...

follow us on twitter

Find us on Facebook

EC&M Whitepaper

Arc Mitigation –A Three-Step Approach

Did you know that an arc-flash incident hospitalizes 5-7 workers per day in North America, severely impacting processes and profitability with lost production? Download This Sponsored Whitepaper Today!

Grounding Versus Bonding
Date: Thursday, May 24, 2012
Time: 2:30pm ET


In this 60-minute FREE webinar, Mike Holt of Mike Holt Enterprises, Inc. will explain the purpose of grounding and bonding as related to the most current requirements set forth in the 2011 NEC. Register Today!

resources

product info icon

product info

tradeshow icon

tradeshow

research icon

research

industry links

industry links

rss icon

rss

Browse Back Issues

Browse Back Issues